| Assessment Year | 2006 |
|---|---|
| Principal Product | Ladies hosiery |
| NAICS | 315110: Hosiery and Sock Mills |
| SIC | 2252: Hosiery, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 152 |
| Plant Area |
115,000
ft2
|
| Annual Production | 24,000,000
pieces
|
| Production Hrs. Annual | 4,800
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $174,273 | 5,721,340 |
kWh
|
$0.030 |
| Electricity Demand | $159,535 | 16,576 |
kW-mo/yr
|
$9.62 |
| Electricity Fees | $10,831 | - |
|
- |
| Natural Gas | $261,814 | 28,349 |
MMBtu
|
$9.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,811 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,850 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $12,717 | $12,000 | - | - |
$12,717
-
MMBtu
|
- | - | - | |
| 02 | 3.4113: Treat and reuse rinse waters | $6,045 | $17,292 | - | - |
$2,625
-
MMBtu
|
$3,420
-
Tgal
|
- | - | |
| 03 | 2.7124: Make a practice of turning off lights when not needed | $592 | $1,000 |
$592
18,496
kWh
|
- | - | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $935 | $100 |
$1,038
32,432
kWh
|
$797
-
kW-mo/yr
|
- | - | $(-600.0) | $(-300.0) | |
| 05 | 2.7313: Recycle air for heating, ventilation and air conditioning | $1,986 | $1,250 |
$143
4,455
kWh
|
$1,843
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.1133: Adjust burners for efficient operation | $4,323 | $1,000 | - | - |
$4,323
-
MMBtu
|
- | - | - | |
| 07 | 2.2123: Insulate feedwater tank | $676 | $1,087 | - | - |
$676
-
MMBtu
|
- | - | - | |
| 08 | 2.6242: Minimize operation of equipment maintained in standby condition | $2,537 | - | - | - |
$2,537
-
MMBtu
|
- | - | - | |
| TOTAL RECOMMENDED | $29,811 | $33,729 |
$1,773
55,383
kWh
|
$2,640
-
kW-mo/yr
|
$22,878
-
MMBtu
|
$3,420
-
Tgal
|
$(-600.0) | $(-300.0) | ||
| TOTAL IMPLEMENTED | $5,850 | $2,100 |
$1,630
50,928
kWh
|
$797
-
kW-mo/yr
|
$4,323
-
MMBtu
|
- | $(-600.0) | $(-300.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs