ITAC Assessment: NC0342
ITAC logo
ITAC Assessment: NC0342
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Ladies hosiery
NAICS 315110: Hosiery and Sock Mills
SIC 2252: Hosiery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 152
Plant Area 115,000
ft2
Annual Production 24,000,000
pieces
Production Hrs. Annual 4,800
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $174,273 5,721,340
kWh
Electricity Demand $159,535 16,576
kW-mo/yr
Electricity Fees $10,831 -
Natural Gas $261,814 28,349
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,811 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,850

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2449: Recover heat from exhausted steam, hot air or hot water $12,717 $12,000 - - $12,717
-
MMBtu
- - -
02 3.4113: Treat and reuse rinse waters $6,045 $17,292 - - $2,625
-
MMBtu
$3,420
-
Tgal
- -
03 2.7124: Make a practice of turning off lights when not needed $592 $1,000 $592
18,496
kWh
- - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $935 $100 $1,038
32,432
kWh
$797
-
kW-mo/yr
- - $(-600.0) $(-300.0)
05 2.7313: Recycle air for heating, ventilation and air conditioning $1,986 $1,250 $143
4,455
kWh
$1,843
-
kW-mo/yr
- - - -
06 2.1133: Adjust burners for efficient operation $4,323 $1,000 - - $4,323
-
MMBtu
- - -
07 2.2123: Insulate feedwater tank $676 $1,087 - - $676
-
MMBtu
- - -
08 2.6242: Minimize operation of equipment maintained in standby condition $2,537 - - - $2,537
-
MMBtu
- - -
TOTAL RECOMMENDED $29,811 $33,729 $1,773
55,383
kWh
$2,640
-
kW-mo/yr
$22,878
-
MMBtu
$3,420
-
Tgal
$(-600.0) $(-300.0)
TOTAL IMPLEMENTED $5,850 $2,100 $1,630
50,928
kWh
$797
-
kW-mo/yr
$4,323
-
MMBtu
- $(-600.0) $(-300.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs