| Assessment Year | 2017 |
|---|---|
| Principal Product | metal can ends |
| NAICS | 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive) |
| SIC | 3466: Crowns and Closures |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
131,000
ft2
|
| Annual Production | 1,980,000,000
units
|
| Production Hrs. Annual | 8,208
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $282,310 | 4,628,075 |
kWh
|
$0.061 | |
| Electricity Demand | $97,531 | 8,877 |
kW-mo/yr
|
$10.99 | |
| Natural Gas | $7,679 | 1,193 |
MMBtu
|
$6.44 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,633 | 329 |
Tgal
|
$8.00 | |
| Water Disposal | $700 | 346 |
Tgal
|
$2.03 | |
| TOTAL YEARLY COSTS | $390,853 | ||||
| RECOMMENDED SAVINGS* | $117,932 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $64,409 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $47,716 | $83,867 |
$31,999
524,576
kWh
|
$9,473
-
kW-mo/yr
|
- | $6,244 | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $37,949 | $3,000 |
$37,949
622,126
kWh
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $16,093 | $1,430 |
$16,093
263,831
kWh
|
- | - | - | |
| 04 | 2.4224: Upgrade controls on compressors | $11,774 | $40,000 |
$9,308
152,592
kWh
|
$2,466
-
kW-mo/yr
|
- | - | |
| 05 | 2.7446: Utilize sensors controlling roof and wall openings | $3,800 | $1,200 |
$3,800
62,297
kWh
|
- | - | - | |
| 06 | 2.4151: Develop a repair/replace policy | $403 | $678 |
$216
3,548
kWh
|
$187
-
kW-mo/yr
|
- | - | |
| 07 | 2.7261: Install timers and/or thermostats | $197 | $100 |
$156
2,563
kWh
|
- |
$41
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $117,932 | $130,275 |
$99,521
1,631,533
kWh
|
$12,126
-
kW-mo/yr
|
$41
-
MMBtu
|
$6,244 | ||
| TOTAL IMPLEMENTED | $64,409 | $86,075 |
$48,464
794,518
kWh
|
$9,660
-
kW-mo/yr
|
$41
-
MMBtu
|
$6,244 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs