| Assessment Year | 1988 |
|---|---|
| Principal Product | FOLDING PAPER CARTONS |
| NAICS |
n/a
|
| SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
| Sales Range | $10 M to 50M |
| # of Employees | 275 |
| Plant Area |
n/a
|
| Annual Production | 19,693
ton
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Delaware |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $321,773 | 6,291,911 |
kWh
|
$0.051 |
| Natural Gas | $62,682 | 14,078 |
MMBtu
|
$4.45 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $45,940 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $32,810 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,542 | $2,386 |
$6,542
128,077
kWh
|
- | |
| 02 | 2.6232: Install set-back timers | $6,581 | - |
$6,581
128,957
kWh
|
- | |
| 03 | 2.4312: Improve lubrication practices | $874 | $1,600 |
$874
16,999
kWh
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,137 | $72 |
$1,137
22,274
kWh
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,757 | - |
$11,757
230,657
kWh
|
- | |
| 06 | 2.6218: Turn off equipment when not in use | $4,115 | - |
$4,115
80,598
kWh
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $3,864 | $5,019 |
$3,864
75,909
kWh
|
- | |
| 08 | 2.6218: Turn off equipment when not in use | $279 | $800 |
$279
5,569
kWh
|
- | |
| 09 | 2.7243: Improve air circulation with destratification fans / other methods | $3,548 | $4,140 |
$(-279.0)
(-5,569)
kWh
|
$3,827
-
MMBtu
|
|
| 10 | 2.7261: Install timers and/or thermostats | $3,707 | $2,151 | - |
$3,707
-
MMBtu
|
|
| 11 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,536 | $500 | - |
$3,536
-
MMBtu
|
|
| TOTAL RECOMMENDED | $45,940 | $16,668 |
$34,870
683,471
kWh
|
$11,070
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $32,810 | $3,686 |
$29,274
573,858
kWh
|
$3,536
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs