ITAC Assessment: AM0468
ITAC logo
ITAC Assessment: AM0468
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Oil pressure blowout preventors and drilling valves
NAICS 333132: Oil and Gas Field Machinery and Equipment Manufacturing
SIC 3491: Industrial Valves
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 79,000
ft2
Annual Production 1,200
pieces
Production Hrs. Annual 2,916
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $84,782 1,079,668
kWh
Electricity Demand $12,855 4,723
kW-mo/yr
Electricity Fees $7,176 -
Natural Gas $42,400 4,617
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,660 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,690

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.3212: Optimize plant power factor $3,870 $14,200 n/a - $3,870
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,520 $800 $1,100
19,650
kWh
$420
-
kW-mo/yr
- -
03 2.4322: Use or replace with energy efficient substitutes $1,510 $760 $1,510
26,910
kWh
- - -
04 2.3212: Optimize plant power factor $1,100 $4,590 - $1,100
-
kW-mo/yr
- -
05 2.7124: Make a practice of turning off lights when not needed $270 $110 $210
3,800
kWh
$60
-
kW-mo/yr
- -
06 2.8121: Apply for tax-free status for energy purchases $37,000 - - - - $37,000
07 2.8123: Pay utility bills on time $390 - - - $390 -
TOTAL RECOMMENDED $45,660 $20,460 $2,820
50,360
kWh
$5,450
-
kW-mo/yr
$390 $37,000
TOTAL IMPLEMENTED $40,690 $1,670 $2,820
50,360
kWh
$480
-
kW-mo/yr
$390 $37,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs