Assessment Year | 2025 |
---|---|
Principal Product | Bulk plastic and steel tubes for fuel and coolant applications |
NAICS | 336340: Motor Vehicle Brake System Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 132 |
Plant Area |
215,000
ft2
|
Annual Production | 393,700
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $764,173 | 14,917,506 |
kWh
|
$0.051 | |
Electricity Demand | $800,649 | 35,785 |
kW-mo/yr
|
$22.37 | |
Electricity Fees | $67,546 | - |
|
- | |
Natural Gas | $210,687 | 31,122 |
MMBtu
|
$6.77 | |
Other Energy | $8,548 | 1 |
MMBtu
|
$8,548.00 | |
Waste Disposal Costs | |||||
Water Usage | $31,585 | 5,766 |
Tgal
|
$5.48 | |
Water Disposal | $34,012 | 5,766 |
Tgal
|
$5.90 | |
Other Liquid (non-haz) | $352 | 1 |
gal
|
$352.03 | |
TOTAL YEARLY COSTS | $1,917,552 | ||||
RECOMMENDED SAVINGS* | $171,769 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $6,486 | $5,850 | - | - |
$6,486
-
MMBtu
|
- | |
02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $25,072 | $83,850 |
$4,552
91,041
kWh
|
$20,520
-
kW-mo/yr
|
- | - | |
03 | 2.3132: Recharge batteries on during off-peak demand periods | $21,996 | $361 | - |
$21,647
-
kW-mo/yr
|
- | $349 | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,419 | - |
$8,563
171,252
kWh
|
$5,856
-
kW-mo/yr
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $5,424 | $305 |
$5,324
106,472
kWh
|
$101
-
kW-mo/yr
|
- | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $39,818 | $496,424 |
$37,365
747,301
kWh
|
$2,453
-
kW-mo/yr
|
- | - | |
07 | 2.4239: Eliminate or reduce compressed air usage | $11,750 | $79,396 |
$6,573
131,460
kWh
|
$5,177
-
kW-mo/yr
|
- | - | |
08 | 2.4322: Use or replace with energy efficient substitutes | $3,961 | $35,691 |
$3,715
74,294
kWh
|
$246
-
kW-mo/yr
|
- | - | |
09 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $2,331 | $1,688 |
$1,302
26,037
kWh
|
$1,029
-
kW-mo/yr
|
- | - | |
10 | 2.6125: Keep equipment clean | $1,393 | - |
$779
15,579
kWh
|
$614
-
kW-mo/yr
|
- | - | |
11 | 2.6218: Turn off equipment when not in use | $495 | - |
$277
5,538
kWh
|
$218
-
kW-mo/yr
|
- | - | |
12 | 2.6232: Install set-back timers | $35,464 | $50,350 |
$4,510
90,201
kWh
|
$4,804
-
kW-mo/yr
|
$26,149
-
MMBtu
|
- | |
13 | 2.7135: Install occupancy sensors | $751 | $541 |
$409
8,176
kWh
|
$342
-
kW-mo/yr
|
- | - | |
14 | 2.7224: Reduce space conditioning during non-working hours | $137 | - | - | - |
$137
-
MMBtu
|
- | |
15 | 2.7261: Install timers and/or thermostats | $2,121 | $1,483 |
$1,186
23,725
kWh
|
$935
-
kW-mo/yr
|
- | - | |
16 | 2.7444: Close holes and openings in building such as broken windows | $152 | $753 | - | - |
$152
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $171,769 | $756,692 |
$74,554
1,491,075
kWh
|
$63,943
-
kW-mo/yr
|
$32,924
-
MMBtu
|
$349 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs