ITAC Assessment: KU0373
ITAC logo
ITAC Assessment: KU0373
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product FABRICATED METAL PRODUCT
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 65
Plant Area
n/a
Annual Production 1,250,000
lb
Production Hrs. Annual 3,400
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $34,096 404,748
kWh
Natural Gas $8,096 1,908
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,629 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $602

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $823 $3,076 - $823
-
MMBtu
02 2.7261: Install timers and/or thermostats $793 $935 - $793
-
MMBtu
03 2.4323: Use optimum size and capacity equipment $572 $385 - $572
-
MMBtu
04 2.6232: Install set-back timers $543 $570 $543
6,448
kWh
-
05 2.2437: Recover waste heat from equipment $331 $101 - $331
-
MMBtu
06 2.4239: Eliminate or reduce compressed air usage $296 $320 $296
3,517
kWh
-
07 2.4221: Install compressor air intakes in coolest locations $271 $180 $271
3,224
kWh
-
TOTAL RECOMMENDED $3,629 $5,567 $1,110
13,189
kWh
$2,519
-
MMBtu
TOTAL IMPLEMENTED $602 $281 $271
3,224
kWh
$331
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs