Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,223

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
UD0292 #03 Y:1989 Reschedule plant operations or reduce load to avoid peaks $1,528 -
UD0292 #02 Y:1989 Utilize higher efficiency lamps and/or ballasts $1,465 $233
UD0292 #01 Y:1989 Use proper thickness of insulation on building envelope $664 $2,400
UD0291 #05 Y:1989 Lower temperature during the winter season and vice-versa $1,866 $2,000
UD0291 #04 Y:1989 Use direct air supply to exhaust hoods $2,237 $4,000
UD0291 #03 Y:1989 Use only amount of air necessary to prevent explosion hazard $851 $500
UD0291 #02 Y:1989 Replace electrically-operated equipment with fossil fuel equipment $2,832 $15,000
UD0291 #01 Y:1989 Replace electrically-operated equipment with fossil fuel equipment $2,548 $6,000
UD0290 #06 Y:1989 Reduce illumination to minimum necessary levels $2,146 $465
UD0290 #05 Y:1989 Reduce glazed areas in buildings $22,077 $21,750
UD0290 #04 Y:1989 Keep lamps and reflectors clean $6,394 $11,600
UD0290 #03 Y:1989 Recover waste heat from equipment $2,035 $3,000
UD0290 #02 Y:1989 Use waste heat from hot flue gases to preheat $5,658 $8,000
UD0290 #01 Y:1989 Combine utility meters $2,104 $1,000
RU0058 #06 Y:1989 Use cooling tower or economizer to replace chiller cooling $16,605 $11,500
RU0058 #05 Y:1989 Air condition only space necessary $2,996 $7,200
RU0058 #04 Y:1989 Install compressor air intakes in coolest locations $3,672 $594
RU0058 #03 Y:1989 Reschedule plant operations or reduce load to avoid peaks $13,950 $2,500
RU0058 #02 Y:1989 Eliminate leaks in inert gas and compressed air lines/ valves $2,807 -
RU0058 #01 Y:1989 Utilize higher efficiency lamps and/or ballasts $3,613 $446