ITAC Assessment: UD0292
ITAC logo
ITAC Assessment: UD0292
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product ASSEMBLY OF MECHANICAL DEVICE
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,545 1,106,975
kWh
Natural Gas $4,949 1,122
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,239 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,465

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7492: Use proper thickness of insulation on building envelope $664 $2,400 - $664
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,465 $233 $1,465
21,395
kWh
- -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,528 - $1,600
-
kWh
- $(-72.0)
04 2.7226: Use computer programs to optimize hvac performance $2,582 $15,000 $2,582
37,515
kWh
- -
TOTAL RECOMMENDED $6,239 $17,633 $5,647
58,910
kWh
$664
-
MMBtu
$(-72.0)
TOTAL IMPLEMENTED $1,465 $233 $1,465
21,395
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs