Assessment Year | 1989 |
---|---|
Principal Product | ASSEMBLY OF MECHANICAL DEVICE |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 80 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,545 | 1,106,975 |
kWh
|
$0.057 |
Natural Gas | $4,949 | 1,122 |
MMBtu
|
$4.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,239 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,465 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7492: Use proper thickness of insulation on building envelope | $664 | $2,400 | - |
$664
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,465 | $233 |
$1,465
21,395
kWh
|
- | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,528 | - |
$1,600
-
kWh
|
- | $(-72.0) | |
04 | 2.7226: Use computer programs to optimize hvac performance | $2,582 | $15,000 |
$2,582
37,515
kWh
|
- | - | |
TOTAL RECOMMENDED | $6,239 | $17,633 |
$5,647
58,910
kWh
|
$664
-
MMBtu
|
$(-72.0) | ||
TOTAL IMPLEMENTED | $1,465 | $233 |
$1,465
21,395
kWh
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs