ITAC Assessment: RU0058
ITAC logo
ITAC Assessment: RU0058
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product PLASTIC LIDS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 104
Plant Area
n/a
Annual Production 550,000
pieces
Production Hrs. Annual 6,864
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $520,999 7,116,061
kWh
Natural Gas $18,575 3,783
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $43,643 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,613 $446 $3,613
49,238
kWh
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,807 - $2,807
38,394
kWh
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $13,950 $2,500 $13,950
-
kWh
04 2.4221: Install compressor air intakes in coolest locations $3,672 $594 $3,672
50,117
kWh
05 2.7229: Air condition only space necessary $2,996 $7,200 $2,996
41,032
kWh
06 2.2614: Use cooling tower or economizer to replace chiller cooling $16,605 $11,500 $16,605
226,846
kWh
TOTAL RECOMMENDED $43,643 $22,240 $43,643
405,627
kWh
TOTAL IMPLEMENTED - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs