Assessment Year | 1989 |
---|---|
Principal Product | PLASTIC LIDS |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 104 |
Plant Area |
n/a
|
Annual Production | 550,000
pieces
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $520,999 | 7,116,061 |
kWh
|
$0.073 |
Natural Gas | $18,575 | 3,783 |
MMBtu
|
$4.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,643 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,613 | $446 |
$3,613
49,238
kWh
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,807 | - |
$2,807
38,394
kWh
|
|
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $13,950 | $2,500 |
$13,950
-
kWh
|
|
04 | 2.4221: Install compressor air intakes in coolest locations | $3,672 | $594 |
$3,672
50,117
kWh
|
|
05 | 2.7229: Air condition only space necessary | $2,996 | $7,200 |
$2,996
41,032
kWh
|
|
06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $16,605 | $11,500 |
$16,605
226,846
kWh
|
|
TOTAL RECOMMENDED | $43,643 | $22,240 |
$43,643
405,627
kWh
|
||
TOTAL IMPLEMENTED | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs