Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

832

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
MU0073 #07 Y:2025 Insulate glazing, walls, ceilings, and roofs $1,669 $2,444
MU0073 #06 Y:2025 Utilize higher efficiency lamps and/or ballasts $22 $118
MU0073 #05 Y:2025 Use photocell controls $50 $107
MU0073 #04 Y:2025 Use or replace with energy efficient substitutes $1,348 $296
MU0073 #03 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $39 $120
MU0073 #02 Y:2025 Reduce the pressure of compressed air to the minimum required $2,226 -
MU0073 #01 Y:2025 Install vinyl strip / high speed / air curtain doors $9,175 $8,435
MU0072 #08 Y:2025 Lease / purchase baler; sell cardboard to recycler $640 -
MU0072 #07 Y:2025 Lower temperature during the winter season and vice-versa $231 -
MU0072 #06 Y:2025 Lower temperature during the winter season and vice-versa $228 -
MU0072 #05 Y:2025 Use photocell controls $138 $404
MU0072 #04 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $1,343 $9,811
MU0072 #03 Y:2025 Recover waste heat from equipment $38 $271
MU0072 #02 Y:2025 Install occupancy sensors $1,481 $960
MU0072 #01 Y:2025 Use heat in flue gases to preheat products or materials $161,393 $126,876
MU0071 #04 Y:2025 Utilize higher efficiency lamps and/or ballasts $442 $1,277
MU0071 #03 Y:2025 Install occupancy sensors $1,188 $3,637
MU0071 #02 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $2,851 $577
MU0071 #01 Y:2025 Replace fossil fuel equipment with electrical equipment $25,925 $65,000
MU0070 #14 Y:2025 Pay bills on time to avoid late fees $178 -