170,803
matching recommendations
$
$
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | 2+ Digits Required | |
| 3+ Characters Required for Products | ||
| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| UF0653 #03 Y:2026 | 03 | 2026 | Utilize higher efficiency lamps and/or ballasts | $10,347 | $28,316 |
n/a
|
| UF0653 #02 Y:2026 | 02 | 2026 | Use demand controller or load shedder | $9,772 | $6,163 |
n/a
|
| UF0653 #01 Y:2026 | 01 | 2026 | Use solar heat to make electricty | $109,343 | $322,608 |
n/a
|
| OK1178 #05 Y:2026 | 05 | 2026 | Clean and maintain refrigerant condensers and towers | $5,237 | $4,365 |
n/a
|
| OK1178 #04 Y:2026 | 04 | 2026 | Install occupancy sensors | $11,237 | $3,916 |
n/a
|
| OK1178 #03 Y:2026 | 03 | 2026 | Utilize higher efficiency lamps and/or ballasts | $11,495 | $42,458 |
n/a
|
| OK1178 #02 Y:2026 | 02 | 2026 | Optimize plant power factor | $1,207 | $2,699 |
n/a
|
| OK1178 #01 Y:2026 | 01 | 2026 | Use solar heat to make electricty | $19,887 | $289,920 |
n/a
|
| UF0650 #09 Y:2026 | 09 | 2026 | Replace existing equipment with more suitable substitutes | $25,000 | $3,560 |
n/a
|
| UF0650 #08 Y:2026 | 08 | 2026 | Improve space comfort conditioning | $56,488 | $22,740 |
n/a
|
| UF0650 #07 Y:2026 | 07 | 2026 | Analyze flue gas for proper air/fuel ratio | $5,076 | - |
n/a
|
| UF0650 #06 Y:2026 | 06 | 2026 | Minimize condenser cooling water temperature | $11,638 | $28,395 |
n/a
|
| UF0650 #05 Y:2026 | 05 | 2026 | Substitute compressed air cooling with water or air cooling | $12,689 | $2,700 |
n/a
|
| UF0650 #04 Y:2026 | 04 | 2026 | Reduce the pressure of compressed air to the minimum required | $23,113 | - |
n/a
|
| UF0650 #03 Y:2026 | 03 | 2026 | Utilize controls to operate equipment only when needed | $58,159 | $7,500 |
n/a
|
| UF0650 #02 Y:2026 | 02 | 2026 | Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $203,555 | $244,447 |
n/a
|
| UF0650 #01 Y:2026 | 01 | 2026 | Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $347,581 | $1,529,500 |
n/a
|
| MI0478 #04 Y:2026 | 04 | 2026 | Use demand controller or load shedder | $4,519 | $18,392 |
n/a
|
| MI0478 #03 Y:2026 | 03 | 2026 | Turn off equipment when not in use | $14,074 | $2,600 |
n/a
|
| MI0478 #02 Y:2026 | 02 | 2026 | Lower temperature during the winter season and vice-versa | $27,548 | $480 |
n/a
|