ITAC Assessment: UF0650
ITAC logo
ITAC Assessment: UF0650
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Fiber-Based Tableware
NAICS 322220: Paper Bag and Coated and Treated Paper Manufacturing
SIC 3497: Metal Foil and Leaf
Sales Range $10
M
to 50
M
# of Employees 149
Plant Area 550,000
ft2
Annual Production 9,490
ton
Production Hrs. Annual 8,400
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,890,121 45,436,320
kWh
Electricity Fees $281,375 -
Natural Gas $169,197 21,000
MMBtu
Waste Disposal Costs
Water Usage $1,200,000 131,000
Tgal
Water Disposal $238,000 30,000
Tgal
TOTAL YEARLY COSTS $4,778,693
RECOMMENDED SAVINGS* $743,299 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $347,581 $1,529,500 $537,600
8,400,000
kWh
$(-106,019.0)
-
MMBtu
$(-84,000.0)
02 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $203,555 $244,447 $203,555
3,180,542
kWh
- -
03 2.6231: Utilize controls to operate equipment only when needed $58,159 $7,500 $58,159
908,726
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $23,113 - $23,113
361,140
kWh
- -
05 2.4237: Substitute compressed air cooling with water or air cooling $12,689 $2,700 $12,689
198,273
kWh
- -
06 2.2623: Minimize condenser cooling water temperature $11,638 $28,395 $11,638
181,838
kWh
- -
07 2.1233: Analyze flue gas for proper air/fuel ratio $5,076 - - $5,076
-
MMBtu
-
08 4.424: Improve space comfort conditioning $56,488 $22,740 $(-1,752.0)
(-27,382)
kWh
- $58,240
09 4.652: Replace existing equipment with more suitable substitutes $25,000 $3,560 - - $25,000
TOTAL RECOMMENDED $743,299 $1,838,842 $845,002
13,203,137
kWh
$(-100,943.0)
-
MMBtu
$(-760.0)
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs