Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

96

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Primary metal products, not elsewhere classified
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
LE0261 #06 Y:2007 Recover waste heat from equipment $7,137 $5,000
LE0261 #05 Y:2007 Reduce the pressure of compressed air to the minimum required $8,661 $100
LE0261 #04 Y:2007 Reduce the pressure of compressed air to the minimum required $15,461 $20
LE0261 #03 Y:2007 Use adjustable frequency drive or multiple speed motors on existing system $17,454 $12,000
LE0261 #02 Y:2007 Use / purchase optimum sized compressor $71,526 $75,000
LE0261 #01 Y:2007 Purchase gas directly from a contract gas supplier $196,792 $500
SU0176 #05 Y:2003 Utilize higher efficiency lamps and/or ballasts $6,095 $13,007
SU0176 #04 Y:2003 Eliminate leaks in inert gas and compressed air lines/ valves $934 $434
SU0176 #03 Y:2003 Use magnetic technology to treat water $2,160 $939
SU0176 #02 Y:2003 Install adequate dryers on air lines to eliminate blowdown $19,192 $4,348
SU0176 #01 Y:2003 Utilize energy-efficient belts and other improved mechanisms $50 -
LE0165 #06 Y:2003 Minimize non-essential material in heat treatment process $3,608 $500
LE0165 #05 Y:2003 Reduce the pressure of compressed air to the minimum required $498 -
LE0165 #04 Y:2003 Turn off equipment when not in use $468 -
LE0165 #03 Y:2003 Reduce illumination to minimum necessary levels $5,356 $263
LE0165 #02 Y:2003 Install occupancy sensors $2,288 $500
LE0165 #01 Y:2003 Insulate bare equipment $8,970 $1,440
LE0157 #06 Y:2003 Install timers on light switches in little used areas $769 $200
LE0157 #05 Y:2003 Utilize energy-efficient belts and other improved mechanisms $1,513 -
LE0157 #04 Y:2003 Use waste heat from hot flue gases to preheat $1,858 $6,500