| Assessment Year | 2003 |
|---|---|
| Principal Product | Thick Film Paste, Solder Paste |
| NAICS | 331492: Secondary Smelting, Refining, and Alloying of Nonferrous Metal (except Copper and Aluminum) |
| SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 95 |
| Plant Area |
62,500
ft2
|
| Annual Production | 100
ton
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $203,222 | 3,382,100 |
kWh
|
$0.060 |
| Electricity Demand | $94,520 | 7,857 |
kW-mo/yr
|
$12.03 |
| Natural Gas | $55,542 | 6,811 |
MMBtu
|
$8.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $134,657 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.651: Install back-up equipment | $125,000 | $30,500 | - | - | - | $125,000 | |
| 02 | 2.6218: Turn off equipment when not in use | $4,881 | - |
$3,366
56,000
kWh
|
$1,515
-
kW-mo/yr
|
- | - | |
| 03 | 2.7135: Install occupancy sensors | $636 | $825 |
$636
10,582
kWh
|
- | - | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $1,858 | $6,500 | - | - |
$1,858
-
MMBtu
|
- | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,513 | - |
$946
15,736
kWh
|
$567
-
kW-mo/yr
|
- | - | |
| 06 | 2.7132: Install timers on light switches in little used areas | $769 | $200 |
$769
12,800
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $134,657 | $38,025 |
$5,717
95,118
kWh
|
$2,082
-
kW-mo/yr
|
$1,858
-
MMBtu
|
$125,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs