Assessment Year | 1997 |
---|---|
Principal Product | Gear Reducers |
NAICS |
n/a
|
SIC | 3566: Speed Changers, Industrial High-Speed Drives, and Gears |
Sales Range | $1 M to 5M |
# of Employees | 90 |
Plant Area |
65,000
ft2
|
Annual Production | 2,400
pieces
|
Production Hrs. Annual | 6,674
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $89,064 | 2,483,294 |
kWh
|
$0.036 |
Electricity Demand | $26,056 | 5,659 |
kW-mo/yr
|
$4.60 |
Natural Gas | $10,380 | 3,256 |
MMBtu
|
$3.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $86,294 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,302 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $1,064 | $27 |
$858
23,740
kWh
|
$206
-
kW-mo/yr
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,328 | $250 |
$1,058
29,308
kWh
|
$270
-
kW-mo/yr
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $346 | $740 |
$224
6,155
kWh
|
$122
-
kW-mo/yr
|
- | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $95 | - |
$57
1,465
kWh
|
$38
-
kW-mo/yr
|
- | - | - | |
05 | 2.3212: Optimize plant power factor | $2,351 | $5,040 | - |
$2,351
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $750 | $90 |
$609
17,585
kWh
|
$141
-
kW-mo/yr
|
- | - | - | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $7,783 | - | - | - | - |
$7,783
-
lb
|
- | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,014 | $15,000 | - | - |
$3,014
-
gal
|
- | - | |
09 | 4.123: Reduce defects by reducing product tipping | $69,563 | $260,000 | - | - | - | - | $69,563 | |
TOTAL RECOMMENDED | $86,294 | $281,147 |
$2,806
78,253
kWh
|
$3,128
-
kW-mo/yr
|
$3,014
-
gal
|
$7,783
-
lb
|
$69,563 | ||
TOTAL IMPLEMENTED | $10,302 | $1,080 |
$1,948
54,513
kWh
|
$571
-
kW-mo/yr
|
- |
$7,783
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs