Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

208

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Copper foundries
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
LM0056 #01 Y:2003 Eliminate leaks in inert gas and compressed air lines/ valves $3,587 $690
IC0024 #14 Y:2001 Move product using mechanical means $11,000 $7,000
IC0024 #13 Y:2001 Clear and rent existing space $365,820 $3,920
IC0024 #12 Y:2001 Recycle casting sand $765,000 -
IC0024 #11 Y:2001 Install set-back timers $2,245 $1,741
IC0024 #10 Y:2001 Install set-back timers $4,823 $968
IC0024 #09 Y:2001 Utilize higher efficiency lamps and/or ballasts $1,134 $945
IC0024 #08 Y:2001 Utilize higher efficiency lamps and/or ballasts $1,811 $7,956
IC0024 #07 Y:2001 Utilize higher efficiency lamps and/or ballasts $9,642 $32,917
IC0024 #06 Y:2001 Upgrade obsolete equipment $9,500 $16,800
IC0024 #05 Y:2001 Eliminate leaks in inert gas and compressed air lines/ valves $13,634 $4,300
IC0024 #04 Y:2001 Use insulation in furnaces to facilitate heating / cooling $1,943 $4,000
IC0024 #03 Y:2001 Use insulation in furnaces to facilitate heating / cooling $7,403 $2,000
IC0024 #02 Y:2001 Use demand controller or load shedder $11,240 $3,280
IC0024 #01 Y:2001 Relocate oven / furnace to more efficient location $27,240 $6,825
OD0166 #04 Y:2000 Meter waste water $20,038 $6,955
OD0166 #03 Y:2000 Adjust / maintain fork lift trucks for most efficient operation $13,669 $113,000
OD0166 #02 Y:2000 Eliminate leaks in inert gas and compressed air lines/ valves $2,297 $520
OD0166 #01 Y:2000 Utilize higher efficiency lamps and/or ballasts $3,013 $8,525
UM0175 #06 Y:2000 Install waste heat boiler to provide direct power $9,120 $7,313