ITAC Assessment: OD0166
ITAC logo
ITAC Assessment: OD0166
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Copper Plumbing Fittings
NAICS
n/a
SIC 3366: Copper Foundries
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 217,000
ft2
Annual Production 0
units
Production Hrs. Annual 7,200
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $912,337 37,150,352
kWh
Electricity Demand $287,797 68,544
kW-mo/yr
Electricity Fees $260,235 -
LPG $359,404 97,107
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,017 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,013 $8,525 n/a $1,932
78,253
kWh
$1,081
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,297 $520 n/a $2,297
92,907
kWh
- - -
03 2.8227: Adjust / maintain fork lift trucks for most efficient operation $13,669 $113,000 n/a - - $13,669 -
04 3.4155: Meter waste water $20,038 $6,955 n/a - - - $20,038
TOTAL RECOMMENDED $39,017 $129,000 $4,229
171,160
kWh
$1,081
-
kW-mo/yr
$13,669 $20,038
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs