| Assessment Year | 2000 |
|---|---|
| Principal Product | Aluminum Castings |
| NAICS |
n/a
|
| SIC | 3366: Copper Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 62 |
| Plant Area |
92,000
ft2
|
| Annual Production | 1,000
ton
|
| Production Hrs. Annual | 2,470
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $233,799 | 2,484,760 |
kWh
|
$0.094 |
| Electricity Fees | $2,881 | - |
|
- |
| Natural Gas | $51,076 | 12,847 |
MMBtu
|
$3.98 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,009 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,249 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $455 | $1,000 |
$455
4,689
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,249 | $600 |
$4,249
43,376
kWh
|
- | - | |
| 03 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $4,332 | $6,000 | - |
$4,332
-
MMBtu
|
- | |
| 04 | 2.2511: Insulate bare equipment | $1,824 | $2,288 | - |
$1,824
-
MMBtu
|
- | |
| 05 | 2.2515: Use optimum thickness insulation | $3,029 | $1,324 | - |
$3,029
-
MMBtu
|
- | |
| 06 | 2.2421: Install waste heat boiler to provide direct power | $9,120 | $7,313 | - | - |
$9,120
-
gal
|
|
| TOTAL RECOMMENDED | $23,009 | $18,525 |
$4,704
48,065
kWh
|
$9,185
-
MMBtu
|
$9,120
-
gal
|
||
| TOTAL IMPLEMENTED | $4,249 | $600 |
$4,249
43,376
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs