ITAC Assessment: UM0175
ITAC logo
ITAC Assessment: UM0175
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Aluminum Castings
NAICS
n/a
SIC 3366: Copper Foundries
Sales Range $10
M
to 50
M
# of Employees 62
Plant Area 92,000
ft2
Annual Production 1,000
ton
Production Hrs. Annual 2,470
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $233,799 2,484,760
kWh
Electricity Fees $2,881 -
Natural Gas $51,076 12,847
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,009 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,249

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings
01 2.7135: Install occupancy sensors $455 $1,000 $455
4,689
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,249 $600 $4,249
43,376
kWh
- -
03 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $4,332 $6,000 - $4,332
-
MMBtu
-
04 2.2511: Insulate bare equipment $1,824 $2,288 - $1,824
-
MMBtu
-
05 2.2515: Use optimum thickness insulation $3,029 $1,324 - $3,029
-
MMBtu
-
06 2.2421: Install waste heat boiler to provide direct power $9,120 $7,313 - - $9,120
-
gal
TOTAL RECOMMENDED $23,009 $18,525 $4,704
48,065
kWh
$9,185
-
MMBtu
$9,120
-
gal
TOTAL IMPLEMENTED $4,249 $600 $4,249
43,376
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs