| UD0979 #12 Y:2017 | 12 | 2017 | Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $180,631 | $300,000 | |
| UD0979 #11 Y:2017 | 11 | 2017 | Add area lighting switches | $1,666 | $130 | |
| UD0979 #10 Y:2017 | 10 | 2017 | Utilize higher efficiency lamps and/or ballasts | $49,834 | $68,160 | |
| UD0979 #09 Y:2017 | 09 | 2017 | Use optimum thickness insulation | $18,548 | $984 | |
| UD0979 #08 Y:2017 | 08 | 2017 | Use waste heat from hot flue gases to preheat | $15,917 | $12,782 | |
| UD0979 #07 Y:2017 | 07 | 2017 | Upgrade controls on compressors | $13,560 | $30,000 | |
| UD0979 #06 Y:2017 | 06 | 2017 | Eliminate or reduce compressed air usage | $14,206 | $905 | |
| UD0979 #05 Y:2017 | 05 | 2017 | Reduce the pressure of compressed air to the minimum required | $31,331 | $6 | |
| UD0979 #04 Y:2017 | 04 | 2017 | Eliminate leaks in inert gas and compressed air lines/ valves | $33,299 | $1,000 | |
| UD0979 #03 Y:2017 | 03 | 2017 | Meter recycled water (to reduce sewer charges) | $26,438 | $4,500 | |
| UD0979 #02 Y:2017 | 02 | 2017 | Use optimum size and capacity equipment | $7,096 | - | |
| UD0979 #01 Y:2017 | 01 | 2017 | Utilize energy-efficient belts and other improved mechanisms | $14,640 | - | |
| UD0696 #12 Y:2004 | 12 | 2004 | Reduce ventilation air | $1,416 | - | |
| UD0696 #11 Y:2004 | 11 | 2004 | Utilize higher efficiency lamps and/or ballasts | $631 | $486 | |
| UD0696 #10 Y:2004 | 10 | 2004 | Keep doors and windows shut when not on use | $845 | - | |
| UD0696 #09 Y:2004 | 09 | 2004 | Disconnect ballasts | $1,218 | $53 | |
| UD0696 #08 Y:2004 | 08 | 2004 | Improve combustion control capability | $1,617 | - | |
| UD0696 #07 Y:2004 | 07 | 2004 | Reduce the pressure of compressed air to the minimum required | $1,891 | $600 | |
| UD0696 #06 Y:2004 | 06 | 2004 | Purchase new equipment to reduce material use / cost | $6,615 | $13,230 | |
| UD0696 #05 Y:2004 | 05 | 2004 | Use waste heat from hot flue gases to preheat | $9,026 | $2,405 |