ITAC Assessment: WM0233
ITAC logo
ITAC Assessment: WM0233
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Aluminum castings
NAICS 331524: Aluminum Foundries (except Die-Casting)
SIC 3365: Aluminum Foundries
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 91,728
ft2
Annual Production 4,896,947
lb
Production Hrs. Annual 4,160
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $97,399 3,489,344
kWh
Electricity Demand $121,281 10,134
kW-mo/yr
Electricity Fees $206,838 -
Natural Gas $206,291 44,325
MMBtu
Waste Disposal Costs
Water Usage $5,176 724
Tgal
TOTAL YEARLY COSTS $636,985
RECOMMENDED SAVINGS* $111,353 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 4.652: Replace existing equipment with more suitable substitutes $97,017 $800,000 - - $97,017
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,262 $1,500 $6,472
231,159
kWh
$3,790
-
kW-mo/yr
-
03 2.1221: Replace obsolete burners with more efficient ones $2,094 $18,160 - - $2,094
-
MMBtu
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,278 - $572
20,424
kWh
$706
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $373 $3,136 $153
5,467
kWh
$220
-
kW-mo/yr
-
06 2.7221: Lower temperature during the winter season and vice-versa $329 $810 $201
7,179
kWh
$128
-
kW-mo/yr
-
TOTAL RECOMMENDED $111,353 $823,606 $7,398
264,229
kWh
$4,844
-
kW-mo/yr
$99,111
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs