Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

221

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Unsupported plastics profile shapes
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
IP0187 #04 Y:2023 Use proper thickness of insulation on building envelope $238 $1,514
IP0187 #03 Y:2023 Utilize higher efficiency lamps and/or ballasts $8,797 $42,271
IP0187 #02 Y:2023 Install occupancy sensors $242 $74
IP0187 #01 Y:2023 Eliminate leaks in inert gas and compressed air lines/ valves $3,338 -
LE0517 #06 Y:2021 Eliminate or reduce compressed air usage $125 $480
LE0517 #05 Y:2021 Use cooling tower or economizer to replace chiller cooling $7,886 $28,000
LE0517 #04 Y:2021 Use adjustable frequency drive or multiple speed motors on existing system $4,795 $12,000
LE0517 #03 Y:2021 Replace existing chiller with high efficiency model $52,000 $100,000
LE0517 #02 Y:2021 Utilize energy-efficient belts and other improved mechanisms $1,255 $400
LE0517 #01 Y:2021 Reduce the pressure of compressed air to the minimum required $603 $40
DL0196 #08 Y:2021 Use cooling tower or economizer to replace chiller cooling $5,629 $13,777
DL0196 #07 Y:2021 Utilize higher efficiency lamps and/or ballasts $13,469 $18,418
DL0196 #06 Y:2021 Insulate bare equipment $1,842 $2,864
DL0196 #05 Y:2021 Use adjustable frequency drive or multiple speed motors on existing system $1,762 $1,037
DL0196 #04 Y:2021 Conserve energy by efficient use of vending machines $110 $20
DL0196 #03 Y:2021 Install timers and/or thermostats $509 $165
DL0196 #02 Y:2021 Turn off equipment when not in use $849 -
DL0196 #01 Y:2021 Install adequate dryers on air lines to eliminate blowdown $5,944 $6,452
MZ0280 #12 Y:2019 Install compressor air intakes in coolest locations $1,153 $550
MZ0280 #11 Y:2019 Utilize energy-efficient belts and other improved mechanisms $2,072 $1,664