| Assessment Year | 2021 |
|---|---|
| Principal Product | Plastic Tubes |
| NAICS | 326121: Unlaminated Plastics Profile Shape Manufacturing |
| SIC | 3082: Unsupported Plastics Profile Shapes |
| Sales Range | $10 M to 50M |
| # of Employees | 41 |
| Plant Area |
75,000
ft2
|
| Annual Production | 400,000
thousand feet
|
| Production Hrs. Annual | 5,616
hrs
|
| Location (State) | Delaware |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $172,240 | 2,060,902 |
kWh
|
$0.084 |
| Electricity Demand | $34,325 | 5,452 |
kW-mo/yr
|
$6.30 |
| LPG | $6,838 | 440 |
MMBtu
|
$15.54 |
| TOTAL YEARLY COSTS | $213,403 | |||
| RECOMMENDED SAVINGS* | $30,114 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,160 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $5,944 | $6,452 |
$5,944
72,491
kWh
|
|
| 02 | 2.6218: Turn off equipment when not in use | $849 | - |
$849
10,358
kWh
|
|
| 03 | 2.7261: Install timers and/or thermostats | $509 | $165 |
$509
6,211
kWh
|
|
| 04 | 2.6211: Conserve energy by efficient use of vending machines | $110 | $20 |
$110
1,340
kWh
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,762 | $1,037 |
$1,762
21,485
kWh
|
|
| 06 | 2.2511: Insulate bare equipment | $1,842 | $2,864 |
$1,842
22,464
kWh
|
|
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,469 | $18,418 |
$13,469
164,255
kWh
|
|
| 08 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $5,629 | $13,777 |
$5,629
68,646
kWh
|
|
| TOTAL RECOMMENDED | $30,114 | $42,733 |
$30,114
367,250
kWh
|
||
| TOTAL IMPLEMENTED | $16,160 | $21,282 |
$16,160
197,077
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs