| Assessment Year | 2021 |
|---|---|
| Principal Product | Treated Wastewater |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | less than $500 k |
| # of Employees | 3 |
| Plant Area |
1,200,000
ft2
|
| Annual Production | 1,321,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $432,780 | 6,865,240 |
kWh
|
$0.063 |
| Electricity Demand | $172,246 | 14,159 |
kW-mo/yr
|
$12.17 |
| Electricity Fees | $26,859 | - |
|
- |
| TOTAL YEARLY COSTS | $631,885 | |||
| RECOMMENDED SAVINGS* | $269,579 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.5313: Increase amount of waste recovered for resale | $222,602 | $148,332 | - | - | - | $(-145,556.0) | $233,753 | $134,405 | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $17,444 | $99 |
$100,969
-
kWh
|
$(-82,830.0)
-
kW-mo/yr
|
$(-695.0) | - | - | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,637 | $1,885 |
$8,111
128,752
kWh
|
$2,526
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.8114: Change rate schedules or other changes in utility service | $7,999 | $99 |
$8,132
-
kWh
|
$(-557.0)
-
kW-mo/yr
|
$424 | - | - | - | |
| 05 | 2.7241: Install outside air damper / economizer on hvac unit | $4,638 | $9,000 |
$3,421
54,310
kWh
|
$1,217
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,161 | $2,385 |
$2,451
38,923
kWh
|
$650
-
kW-mo/yr
|
- | - | $60 | - | |
| 07 | 2.7135: Install occupancy sensors | $3,098 | $765 |
$3,098
49,180
kWh
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $269,579 | $162,565 |
$126,182
271,165
kWh
|
$(-78,994.0)
-
kW-mo/yr
|
$(-271.0) | $(-145,556.0) | $233,813 | $134,405 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs