ITAC Assessment: AS0511
ITAC logo
ITAC Assessment: AS0511
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Treated Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 3
Plant Area 1,200,000
ft2
Annual Production 1,321,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $432,780 6,865,240
kWh
Electricity Demand $172,246 14,159
kW-mo/yr
Electricity Fees $26,859 -
TOTAL YEARLY COSTS $631,885
RECOMMENDED SAVINGS* $269,579 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings By-product Production Savings
01 3.5313: Increase amount of waste recovered for resale $222,602 $148,332 - - - $(-145,556.0) $233,753 $134,405
02 2.8114: Change rate schedules or other changes in utility service $17,444 $99 $100,969
-
kWh
$(-82,830.0)
-
kW-mo/yr
$(-695.0) - - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,637 $1,885 $8,111
128,752
kWh
$2,526
-
kW-mo/yr
- - - -
04 2.8114: Change rate schedules or other changes in utility service $7,999 $99 $8,132
-
kWh
$(-557.0)
-
kW-mo/yr
$424 - - -
05 2.7241: Install outside air damper / economizer on hvac unit $4,638 $9,000 $3,421
54,310
kWh
$1,217
-
kW-mo/yr
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,161 $2,385 $2,451
38,923
kWh
$650
-
kW-mo/yr
- - $60 -
07 2.7135: Install occupancy sensors $3,098 $765 $3,098
49,180
kWh
- - - - -
TOTAL RECOMMENDED $269,579 $162,565 $126,182
271,165
kWh
$(-78,994.0)
-
kW-mo/yr
$(-271.0) $(-145,556.0) $233,813 $134,405
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs