1,006
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| DL0271 #06 Y:2025 | 06 | 2025 | Utilize energy-efficient belts and other improved mechanisms | $50,040 | $42,000 |
n/a
|
| DL0271 #05 Y:2025 | 05 | 2025 | Provide proper maintenance of motor driven equipment | $48,372 | $50,000 |
n/a
|
| DL0271 #04 Y:2025 | 04 | 2025 | Replace obsolete burners with more efficient ones | $34,850 | $150,000 |
n/a
|
| DL0271 #03 Y:2025 | 03 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $5,725 | $23,500 |
n/a
|
| DL0271 #02 Y:2025 | 02 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $3,040 | $12,900 |
n/a
|
| DL0271 #01 Y:2025 | 01 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $54,924 | $200,000 |
n/a
|
| OK1164 #04 Y:2025 | 04 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $580 | $1,847 |
n/a
|
| OK1164 #03 Y:2025 | 03 | 2025 | Clean and maintain refrigerant condensers and towers | $566 | $780 |
n/a
|
| OK1164 #02 Y:2025 | 02 | 2025 | Replace existing hvac unit with high efficiency model | $1,105 | $3,355 |
n/a
|
| OK1164 #01 Y:2025 | 01 | 2025 | Use solar heat to make electricty | $201,784 | $2,044,800 |
n/a
|
| OR0820 #04 Y:2025 | 04 | 2025 | Redesign flow to minimize mass transfer length | $12,313 | $175,000 |
n/a
|
| OR0820 #03 Y:2025 | 03 | 2025 | Replace hydraulic / pneumatic equipment with electric equipment | $2,066 | $629 |
n/a
|
| OR0820 #02 Y:2025 | 02 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $4,677 | $982 |
n/a
|
| OR0820 #01 Y:2025 | 01 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $10,825 | $10,263 |
n/a
|
| UC2515 #07 Y:2025 | 07 | 2025 | Use or replace with energy efficient substitutes | $3,927 | $15,750 |
n/a
|
| UC2515 #06 Y:2025 | 06 | 2025 | Reduce the pressure of compressed air to the minimum required | $1,176 | - |
n/a
|
| UC2515 #05 Y:2025 | 05 | 2025 | Keep solid fuels / raw materials dry | $23,748 | $104,000 |
n/a
|
| UC2515 #04 Y:2025 | 04 | 2025 | Change rate schedules or other changes in utility service | $102,262 | $420,000 |
n/a
|
| UC2515 #03 Y:2025 | 03 | 2025 | Use solar heat to make electricty | $25,271 | $169,615 |
n/a
|
| UC2515 #02 Y:2025 | 02 | 2025 | Insulate bare equipment | $19,982 | $9,655 |
n/a
|