ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
UF0618 #07 Y:2024 | 07 | 2024 | Improve space comfort conditioning | $10,000 | $1,931 |
n/a
|
UF0618 #06 Y:2024 | 06 | 2024 | Improve air circulation with destratification fans / other methods | $12,621 | $12,380 |
n/a
|
UF0618 #05 Y:2024 | 05 | 2024 | Consider use / purchase of bulk materials where possible | $150,000 | $70,000 |
n/a
|
UF0618 #04 Y:2024 | 04 | 2024 | Add/modify equipment to improve drying process | $308,175 | $14,388 |
n/a
|
UF0618 #03 Y:2024 | 03 | 2024 | Use most efficient type of electric motors | $1,409 | $5,855 |
n/a
|
UF0618 #02 Y:2024 | 02 | 2024 | Use fossil fuel powered generator during peak demand periods | $1,789 | $872 |
n/a
|
UF0618 #01 Y:2024 | 01 | 2024 | Use solar heat to make electricty | $19,157 | $112,913 |
n/a
|
NL0072 #04 Y:2022 | 04 | 2022 | Install compressor air intakes in coolest locations | $773 | $1,445 | |
NL0072 #03 Y:2022 | 03 | 2022 | Use steam condensate for hot water supply (non-potable) | $2,055 | $266 | |
NL0072 #02 Y:2022 | 02 | 2022 | Use adjustable frequency drive or multiple speed motors on existing system | $12,761 | $20,400 | |
NL0072 #01 Y:2022 | 01 | 2022 | Replace boiler | $18,966 | $23,925 | |
MZ0119 #04 Y:2013 | 04 | 2013 | Lower temperature during the winter season and vice-versa | $1,728 | - | |
MZ0119 #03 Y:2013 | 03 | 2013 | Install occupancy sensors | $1,150 | $900 | |
MZ0119 #02 Y:2013 | 02 | 2013 | Utilize higher efficiency lamps and/or ballasts | $8,154 | $14,260 | |
MZ0119 #01 Y:2013 | 01 | 2013 | Recover waste heat from equipment | $2,963 | - | |
AS0376 #03 Y:2003 | 03 | 2003 | Use most efficient type of electric motors | $2,889 | $1,550 | |
AS0376 #02 Y:2003 | 02 | 2003 | Eliminate or reduce compressed air usage | $11,286 | $2,016 | |
AS0376 #01 Y:2003 | 01 | 2003 | Eliminate leaks in inert gas and compressed air lines/ valves | $20,069 | $60 | |
GT0606 #08 Y:1996 | 08 | 1996 | Change procedures / equipment / operating conditions | $3,074 | $10,500 | |
GT0606 #07 Y:1996 | 07 | 1996 | Install timers on light switches in little used areas | $1,067 | $350 |