1,923
matching recommendations
$
$
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | Sawmills and planing mills, general | |
| 3+ Characters Required for Products | ||
| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| OR0816 #05 Y:2025 | 05 | 2025 | Repair or replace steam traps | $5,263 | $45,752 |
n/a
|
| OR0816 #04 Y:2025 | 04 | 2025 | Optimize plant power factor | $18,312 | $120,179 |
n/a
|
| OR0816 #03 Y:2025 | 03 | 2025 | Replace existing hvac unit with high efficiency model | $8,154 | $40,218 |
n/a
|
| OR0816 #02 Y:2025 | 02 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $33,221 | $16,610 |
n/a
|
| OR0816 #01 Y:2025 | 01 | 2025 | Reduce the pressure of compressed air to the minimum required | $12,434 | - |
n/a
|
| MU0071 #04 Y:2025 | 04 | 2025 | Utilize higher efficiency lamps and/or ballasts | $442 | $1,277 |
n/a
|
| MU0071 #03 Y:2025 | 03 | 2025 | Install occupancy sensors | $1,188 | $3,637 |
n/a
|
| MU0071 #02 Y:2025 | 02 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $2,851 | $577 |
n/a
|
| MU0071 #01 Y:2025 | 01 | 2025 | Replace fossil fuel equipment with electrical equipment | $25,925 | $65,000 |
n/a
|
| LT8415 #04 Y:2024 | 04 | 2024 | Change rate schedules or other changes in utility service | $7,019 | - |
n/a
|
| LT8415 #03 Y:2024 | 03 | 2024 | Turn off equipment when not in use | $297 | $496 |
n/a
|
| LT8415 #02 Y:2024 | 02 | 2024 | Make a practice of turning off lights when not needed | $1,473 | - |
n/a
|
| LT8415 #01 Y:2024 | 01 | 2024 | Eliminate leaks in inert gas and compressed air lines/ valves | $19,477 | $355 |
n/a
|
| LT8416 #03 Y:2024 | 03 | 2024 | Re-arrange equipment layout to reduce handling costs | $28,404 | $1,070 |
n/a
|
| LT8416 #02 Y:2024 | 02 | 2024 | Reduce heat gain by window tinting | $455 | $400 |
n/a
|
| LT8416 #01 Y:2024 | 01 | 2024 | Install occupancy sensors | $164 | $118 |
n/a
|
| OR0801 #06 Y:2024 | 06 | 2024 | Use solar heat to make electricty | $6,884 | $92,435 | |
| OR0801 #05 Y:2024 | 05 | 2024 | Utilize higher efficiency lamps and/or ballasts | $1,786 | $5,438 | |
| OR0801 #04 Y:2024 | 04 | 2024 | Reduce the pressure of compressed air to the minimum required | $2,400 | $6,763 | |
| OR0801 #03 Y:2024 | 03 | 2024 | Optimize plant power factor | $15,143 | $44,093 |