Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

34

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Coating, engraving, heat treating, and allied activities
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
LM0123 #04 Y:2006 Train operators for maximum operating efficiency $37,630 $1,000
LM0123 #03 Y:2006 Replace existing hvac unit with high efficiency model $6,789 $20,000
LM0123 #02 Y:2006 Cover open tanks $7,790 $1,800
LM0123 #01 Y:2006 Utilize higher efficiency lamps and/or ballasts $15,533 $33,000
LM0106 #02 Y:2005 Train operators for maximum operating efficiency $33,590 $8,640
LM0106 #01 Y:2005 Cover open tanks $3,315 $1,500
LM0092 #11 Y:2004 Train operators for maximum operating efficiency $1,200 $100
LM0092 #10 Y:2004 Begin a practice of predictive / preventative maintenance $14,473 $100
LM0092 #09 Y:2004 Add equipment/ operators to reduce production bottleneck $98,438 $100,000
LM0092 #08 Y:2004 Maintain/enlarge a stock of spare parts $36,180 $5,000
LM0092 #07 Y:2004 Eliminate or reduce compressed air usage $19,657 $5,000
LM0092 #06 Y:2004 Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $12,597 $5,000
LM0092 #05 Y:2004 Replace heat treating oven with more efficient unit $62,655 $140,000
LM0092 #04 Y:2004 Use most efficient type of electric motors $211 $246
LM0092 #03 Y:2004 Eliminate leaks in inert gas and compressed air lines/ valves $3,281 $170
LM0092 #02 Y:2004 Utilize energy-efficient belts and other improved mechanisms $1,912 $760
LM0092 #01 Y:2004 Utilize higher efficiency lamps and/or ballasts $1,559 $2,640
LM0081 #07 Y:2004 Reduce illumination to minimum necessary levels $4,611 $1,814
LM0081 #06 Y:2004 Maintain clean conditions before painting $292,248 $4,925
LM0081 #05 Y:2004 Maintain clean conditions before painting $233,065 $1,000