| Assessment Year | 2026 |
|---|---|
| Principal Product | Electro-mechanical devices |
| NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $50 M to 100M |
| # of Employees | 360 |
| Plant Area |
125,000
ft2
|
| Annual Production | 150,000
units
|
| Production Hrs. Annual | 5,600
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $214,468 | 3,428,240 |
kWh
|
$0.063 |
| Electricity Demand | $118,026 | 8,453 |
kW-mo/yr
|
$13.96 |
| Electricity Fees | $21,763 | - |
|
- |
| Natural Gas | $18,177 | 2,300 |
MMBtu
|
$7.90 |
| TOTAL YEARLY COSTS | $372,434 | |||
| RECOMMENDED SAVINGS* | $70,417 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,270 | $5,900 |
$12,360
196,200
kWh
|
$4,910
-
kW-mo/yr
|
- | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $5,305 | $12,840 |
$3,920
62,200
kWh
|
$1,385
-
kW-mo/yr
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,137 | $10,470 |
$4,460
70,780
kWh
|
$677
-
kW-mo/yr
|
- | |
| 04 | 2.3141: Use battery storage for demand control | $42,705 | $212,840 | - |
$17,705
-
kW-mo/yr
|
$25,000 | |
| TOTAL RECOMMENDED | $70,417 | $242,050 |
$20,740
329,180
kWh
|
$24,677
-
kW-mo/yr
|
$25,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs