Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

79

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Concrete pipe manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
AM0794 #07 Y:2019 Pay utility bills on time $127 -
AM0794 #06 Y:2019 Reduce the pressure of compressed air to the minimum required $670 $7
AM0794 #05 Y:2019 Use synthetic lubricant $801 $100
AM0794 #04 Y:2019 Reduce the pressure of compressed air to the minimum required $990 $450
AM0794 #03 Y:2019 Make a practice of turning off lights when not needed $1,100 $8
AM0794 #02 Y:2019 Apply for tax-free status for energy purchases $12,250 $2,000
AM0794 #01 Y:2019 Eliminate leaks in inert gas and compressed air lines/ valves $5,215 $2,000
BS0086 #05 Y:2016 Install compressor air intakes in coolest locations $1,268 $147
BS0086 #04 Y:2016 Eliminate leaks in inert gas and compressed air lines/ valves $1,877 $1,280
BS0086 #03 Y:2016 Utilize controls to operate equipment only when needed $2,887 $280
BS0086 #02 Y:2016 Replace boiler $4,643 $61,724
BS0086 #01 Y:2016 Optimize plant power factor $12,315 $14,270
MI0144 #05 Y:2006 Reduce the pressure of compressed air to the minimum required $4,578 $30
MI0144 #04 Y:2006 Reduce illumination to minimum necessary levels $7,878 $135
MI0144 #03 Y:2006 Replace fossil fuel equipment with electrical equipment $8,832 $6,430
MI0144 #02 Y:2006 Utilize higher efficiency lamps and/or ballasts $9,559 $22,932
MI0144 #01 Y:2006 Eliminate leaks in inert gas and compressed air lines/ valves $18,115 $1,074
CO0594 #10 Y:2006 Install / repair insulation on steam lines $360 $90
CO0594 #09 Y:2006 Apply for tax-free status for energy purchases $950 $500
CO0594 #08 Y:2006 Utilize higher efficiency lamps and/or ballasts $990 $3,420