ITAC Assessment: CO0594
ITAC logo
ITAC Assessment: CO0594
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Concrete pipe
NAICS 327332: Concrete Pipe Manufacturing
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $5
M
to 10
M
# of Employees 11
Plant Area 16,000
ft2
Annual Production 40,000
ton
Production Hrs. Annual 2,622
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $15,356 393,200
kWh
Electricity Demand $20,777 2,994
kW-mo/yr
Electricity Fees $813 -
Natural Gas $39,470 4,130
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,710 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2437: Recover waste heat from equipment $4,730 $3,350 - - $4,730
-
MMBtu
- -
02 2.3212: Optimize plant power factor $4,550 $11,320 - $4,550
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,300 $6,900 $1,520
37,200
kWh
$1,780
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $150 $442 $60
1,365
kWh
$90
-
kW-mo/yr
- - -
05 2.6218: Turn off equipment when not in use $380 - - - $380
-
MMBtu
- -
06 2.7232: Replace existing hvac unit with high efficiency model $3,200 $5,050 - - $3,200
-
MMBtu
- -
07 2.9114: Use solar heat to make electricty $1,100 $2,950 $620
15,200
kWh
$480
-
kW-mo/yr
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $990 $3,420 $450
10,900
kWh
$520
-
kW-mo/yr
- - $20
09 2.8121: Apply for tax-free status for energy purchases $950 $500 - - - $950 -
10 2.2136: Install / repair insulation on steam lines $360 $90 - - $360
-
MMBtu
- -
TOTAL RECOMMENDED $19,710 $34,022 $2,650
64,665
kWh
$7,420
-
kW-mo/yr
$8,670
-
MMBtu
$950 $20
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs