Assessment Year | 2016 |
---|---|
Principal Product | Concrete Pipe |
NAICS | 327332: Concrete Pipe Manufacturing |
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $10 M to 50M |
# of Employees | 112 |
Plant Area |
147,000
ft2
|
Annual Production | 100,500
ton
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $65,704 | 1,684,319 |
kWh
|
$0.039 |
Electricity Demand | $114,001 | 6,941 |
kW-mo/yr
|
$16.42 |
Electricity Fees | $739 | - |
|
- |
Natural Gas | $75,100 | 20,641 |
MMBtu
|
$3.64 |
TOTAL YEARLY COSTS | $255,545 | |||
RECOMMENDED SAVINGS* | $22,990 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,764 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $12,315 | $14,270 | - | - | $12,315 | - | |
02 | 2.1224: Replace boiler | $4,643 | $61,724 |
$(-3,370.0)
(-86,386)
kWh
|
- | - |
$8,013
-
MMBtu
|
|
03 | 2.6231: Utilize controls to operate equipment only when needed | $2,887 | $280 |
$2,887
74,009
kWh
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,877 | $1,280 |
$1,877
48,127
kWh
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,268 | $147 |
$726
18,261
kWh
|
$542
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $22,990 | $77,701 |
$2,120
54,011
kWh
|
$542
-
kW-mo/yr
|
$12,315 |
$8,013
-
MMBtu
|
||
TOTAL IMPLEMENTED | $4,764 | $1,560 |
$4,764
122,136
kWh
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs