ITAC Assessment: BS0086
ITAC logo
ITAC Assessment: BS0086
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Concrete Pipe
NAICS 327332: Concrete Pipe Manufacturing
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 112
Plant Area 147,000
ft2
Annual Production 100,500
ton
Production Hrs. Annual 2,730
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $65,704 1,684,319
kWh
Electricity Demand $114,001 6,941
kW-mo/yr
Electricity Fees $739 -
Natural Gas $75,100 20,641
MMBtu
TOTAL YEARLY COSTS $255,545
RECOMMENDED SAVINGS* $22,990 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,764

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $12,315 $14,270 - - $12,315 -
02 2.1224: Replace boiler $4,643 $61,724 $(-3,370.0)
(-86,386)
kWh
- - $8,013
-
MMBtu
03 2.6231: Utilize controls to operate equipment only when needed $2,887 $280 $2,887
74,009
kWh
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,877 $1,280 $1,877
48,127
kWh
- - -
05 2.4221: Install compressor air intakes in coolest locations $1,268 $147 $726
18,261
kWh
$542
-
kW-mo/yr
- -
TOTAL RECOMMENDED $22,990 $77,701 $2,120
54,011
kWh
$542
-
kW-mo/yr
$12,315 $8,013
-
MMBtu
TOTAL IMPLEMENTED $4,764 $1,560 $4,764
122,136
kWh
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs