32
matching recommendations
$
$
| ARC | 2+ Digits Required | |
| NAICS | Glass product manufacturing made of purchased glass | |
| SIC | 2+ Digits Required | |
| 3+ Characters Required for Products | ||
| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| MI0172 #08 Y:2008 | 08 | 2008 | Utilize energy-efficient belts and other improved mechanisms | $728 | $1,200 | |
| MI0172 #07 Y:2008 | 07 | 2008 | Reduce the pressure of compressed air to the minimum required | $2,251 | $24 | |
| MI0172 #06 Y:2008 | 06 | 2008 | Eliminate leaks in inert gas and compressed air lines/ valves | $4,883 | $1,210 | |
| MI0172 #05 Y:2008 | 05 | 2008 | Reduce the pressure of compressed air to the minimum required | $343 | $24 | |
| MI0172 #04 Y:2008 | 04 | 2008 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,695 | $1,210 | |
| MI0172 #03 Y:2008 | 03 | 2008 | Utilize higher efficiency lamps and/or ballasts | $9,860 | $8,778 | |
| MI0172 #02 Y:2008 | 02 | 2008 | Use adjustable frequency drive or multiple speed motors on existing system | $86,926 | $83,640 | |
| MI0172 #01 Y:2008 | 01 | 2008 | Reschedule breaks to allow for continuous production | $126,000 | $66,640 | |
| MI0136 #06 Y:2006 | 06 | 2006 | Change rate schedules or other changes in utility service | $1,680 | $100 | |
| MI0136 #05 Y:2006 | 05 | 2006 | Utilize energy-efficient belts and other improved mechanisms | $1,760 | - | |
| MI0136 #04 Y:2006 | 04 | 2006 | Reduce the pressure of compressed air to the minimum required | $2,010 | $2,506 | |
| MI0136 #03 Y:2006 | 03 | 2006 | Eliminate leaks in inert gas and compressed air lines/ valves | $3,741 | $1,074 | |
| MI0136 #02 Y:2006 | 02 | 2006 | Reduce illumination to minimum necessary levels | $4,544 | $146 | |
| MI0136 #01 Y:2006 | 01 | 2006 | Use adjustable frequency drive or multiple speed motors on existing system | $36,851 | $40,224 | |
| MI0112 #05 Y:2005 | 05 | 2005 | Eliminate or reduce compressed air usage | $3,504 | $1,393 | |
| MI0112 #04 Y:2005 | 04 | 2005 | Change rate schedules or other changes in utility service | $6,289 | $600 | |
| MI0112 #03 Y:2005 | 03 | 2005 | Replace existing equipment with more suitable substitutes | $19,066 | $8,226 | |
| MI0112 #02 Y:2005 | 02 | 2005 | Apply for tax-free status for energy purchases | $89,581 | $90 | |
| MI0112 #01 Y:2005 | 01 | 2005 | Add equipment/ operators to reduce production bottleneck | $319,237 | $91,320 | |