ITAC Assessment: MI0112
ITAC logo
ITAC Assessment: MI0112
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Glass Manufacturer
NAICS 327215: Glass Product Manufacturing Made of Purchased Glass
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 73,000
ft2
Annual Production 3,750,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $255,833 5,059,200
kWh
Electricity Demand $120,239 14,601
kW-mo/yr
Electricity Fees $70,900 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $437,677 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $118,440

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Increase in Production Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $319,237 $91,320 $7,699
155,893
kWh
- - $311,538
02 2.8121: Apply for tax-free status for energy purchases $89,581 $90 - - $89,581 -
03 4.652: Replace existing equipment with more suitable substitutes $19,066 $8,226 $14,718
297,310
kWh
$4,348
-
kW-mo/yr
- -
04 2.8114: Change rate schedules or other changes in utility service $6,289 $600 - - $6,289 -
05 2.4239: Eliminate or reduce compressed air usage $3,504 $1,393 $3,504
61,361
kWh
- - -
TOTAL RECOMMENDED $437,677 $101,629 $25,921
514,564
kWh
$4,348
-
kW-mo/yr
$95,870 $311,538
TOTAL IMPLEMENTED $118,440 $10,309 $18,222
358,671
kWh
$4,348
-
kW-mo/yr
$95,870 -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs