ITAC Assessment: UM0079
ITAC logo
ITAC Assessment: UM0079
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Envelopes
NAICS
n/a
SIC 2699:
Sales Range $10
M
to 50
M
# of Employees 115
Plant Area 45,000
ft2
Annual Production 700,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,432 2,886,284
kWh
Electricity Demand $112,262 6,576
kW-mo/yr
Electricity Fees $(-2,665.0) -
Natural Gas $4,371 1,009
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,385 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,581

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings
01 2.4133: Use most efficient type of electric motors $12,562 $7,260 $8,751
167,057
kWh
$3,811
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $12,062 $24,775 $7,915
127,491
kWh
$4,147
-
kW-mo/yr
- - - -
03 2.4221: Install compressor air intakes in coolest locations $1,078 $1,200 $751
14,361
kWh
$327
-
kW-mo/yr
- - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $4,879 - $4,708
89,683
kWh
$171
-
kW-mo/yr
- - - -
05 3.8143: Recycle cleaning solvent and reuse $2,412 $7,200 - - $451
-
gal
$(-1,784.0) $3,745 -
06 4.121: Maintain clean conditions before painting $2,392 $5 - - - - - $2,392
TOTAL RECOMMENDED $35,385 $40,440 $22,125
398,592
kWh
$8,456
-
kW-mo/yr
$451
-
gal
$(-1,784.0) $3,745 $2,392
TOTAL IMPLEMENTED $30,581 $33,235 $22,125
398,592
kWh
$8,456
-
kW-mo/yr
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs