matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| LE0570 #06 Y:2024 | 06 | 2024 | Install back-up equipment | $46,731 | $90,000 | |
| LE0570 #05 Y:2024 | 05 | 2024 | Install compressor air intakes in coolest locations | $4,252 | $5,000 | |
| LE0570 #04 Y:2024 | 04 | 2024 | Reduce the pressure of compressed air to the minimum required | $25,168 | $26,500 | |
| LE0570 #03 Y:2024 | 03 | 2024 | Use adjustable frequency drive or multiple speed motors on existing system | $55,246 | $42,000 | |
| LE0570 #02 Y:2024 | 02 | 2024 | Use adjustable frequency drive or multiple speed motors on existing system | $33,515 | $15,000 | |
| LE0570 #01 Y:2024 | 01 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $9,292 | - | |
| DL0234 #04 Y:2023 | 04 | 2023 | Repair furnaces and oven doors so that they seal efficiently | $76,734 | $166,100 | |
| DL0234 #03 Y:2023 | 03 | 2023 | Repair furnaces and oven doors so that they seal efficiently | $95,717 | $35,600 | |
| DL0234 #02 Y:2023 | 02 | 2023 | Utilize energy-efficient belts and other improved mechanisms | $21,550 | $30,000 | |
| DL0234 #01 Y:2023 | 01 | 2023 | Isolate hot or cold equipment | $36,400 | $82,500 | |
| LE0472 #06 Y:2019 | 06 | 2019 | Eliminate leaks in inert gas and compressed air lines/ valves | $2,558 | $6,000 | |
| LE0472 #05 Y:2019 | 05 | 2019 | Utilize higher efficiency lamps and/or ballasts | $33,212 | $57,800 | |
| LE0472 #04 Y:2019 | 04 | 2019 | Utilize energy-efficient belts and other improved mechanisms | $208 | $285 | |
| LE0472 #03 Y:2019 | 03 | 2019 | Install compressor air intakes in coolest locations | $3,747 | $2,000 | |
| LE0472 #02 Y:2019 | 02 | 2019 | Turn off equipment when not in use | $7,038 | $1,500 | |
| LE0472 #01 Y:2019 | 01 | 2019 | Eliminate leaks in inert gas and compressed air lines/ valves | $6,354 | $563 | |
| DL0169 #06 Y:2016 | 06 | 2016 | Use adjustable frequency drive or multiple speed motors on existing system | $300,500 | $1,937,040 | |
| DL0169 #05 Y:2016 | 05 | 2016 | Insulate bare equipment | $11,160 | $11,160 | |
| DL0169 #04 Y:2016 | 04 | 2016 | Use hot process fluids to preheat incoming process fluids | $5,060 | $5,000 | |
| DL0169 #03 Y:2016 | 03 | 2016 | Adjust burners for efficient operation | $117,000 | $34,000 |