ITAC Assessment: DL0234
ITAC logo
ITAC Assessment: DL0234
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Gypsum Drywall
NAICS 327420: Gypsum Product Manufacturing
SIC 3275: Gypsum Products
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 200,000
ft2
Annual Production 345,000
ton
Production Hrs. Annual 8,060
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,505,328 19,725,456
kWh
Electricity Demand $41,005 34,608
kW-mo/yr
Electricity Fees $24,456 -
Natural Gas $4,500,127 738,908
MMBtu
TOTAL YEARLY COSTS $7,070,916
RECOMMENDED SAVINGS* $230,401 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2522: Isolate hot or cold equipment $36,400 $82,500 $36,400
280,000
kWh
-
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $21,550 $30,000 $21,550
165,800
kWh
-
03 2.1135: Repair furnaces and oven doors so that they seal efficiently $95,717 $35,600 - $95,717
-
MMBtu
04 2.1135: Repair furnaces and oven doors so that they seal efficiently $76,734 $166,100 - $76,734
-
MMBtu
TOTAL RECOMMENDED $230,401 $314,200 $57,950
445,800
kWh
$172,451
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs