ITAC Assessment: LE0472
ITAC logo
ITAC Assessment: LE0472
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Paving stones
NAICS 327331: Concrete Block and Brick Manufacturing
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $1
M
to 5
M
# of Employees 51
Plant Area 95,000
ft2
Annual Production 150,000
ton
Production Hrs. Annual 7,560
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $589,683 5,947,826
kWh
Electricity Demand $51,915 12,698
kW-mo/yr
Electricity Fees $152,021 -
Natural Gas $68,527 8,379
MMBtu
TOTAL YEARLY COSTS $862,146
RECOMMENDED SAVINGS* $53,117 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $44,205

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,354 $563 $3,336
33,700
kWh
$3,018
-
kW-mo/yr
02 2.6218: Turn off equipment when not in use $7,038 $1,500 $7,038
71,089
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $3,747 $2,000 $3,547
35,828
kWh
$200
-
kW-mo/yr
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $208 $285 $194
1,995
kWh
$14
-
kW-mo/yr
05 2.7142: Utilize higher efficiency lamps and/or ballasts $33,212 $57,800 $31,429
317,466
kWh
$1,783
-
kW-mo/yr
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,558 $6,000 $2,419
24,439
kWh
$139
-
kW-mo/yr
TOTAL RECOMMENDED $53,117 $68,148 $47,963
484,517
kWh
$5,154
-
kW-mo/yr
TOTAL IMPLEMENTED $44,205 $61,585 $42,208
426,378
kWh
$1,997
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs