ITAC Assessment: SF0389
ITAC logo
ITAC Assessment: SF0389
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Treated Wastewater
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range less than $500
k
# of Employees 56
Plant Area 962,737
ft2
Annual Production 6,205,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $192,346 2,131,791
kWh
Electricity Demand $173,227 13,476
kW-mo/yr
Natural Gas $487,708 74,175
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,307 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $44,307

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4235: Remove or close off unneeded compressed air lines $10,049 $400 $8,208
90,967
kWh
$1,841
-
kW-mo/yr
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $255 $31 $209
2,318
kWh
$46
-
kW-mo/yr
- -
03 2.7132: Install timers on light switches in little used areas $6,873 $2,392 $5,751
63,733
kWh
$1,122
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $953 $672 $158
1,751
kWh
$31
-
kW-mo/yr
$470 $294
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,157 $2,712 $2,510
27,823
kWh
$647
-
kW-mo/yr
- -
06 2.7135: Install occupancy sensors $4,881 $7,273 $3,917
43,411
kWh
$964
-
kW-mo/yr
- -
07 2.7134: Use photocell controls $11,135 $19,068 $8,010
88,774
kWh
$3,125
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $2,881 $9,823 $2,402
26,625
kWh
$479
-
kW-mo/yr
- -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,274 $8,179 $1,903
21,090
kWh
$371
-
kW-mo/yr
- -
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,037 $9,053 $867
9,608
kWh
$170
-
kW-mo/yr
- -
11 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $812 $7,156 $679
7,526
kWh
$133
-
kW-mo/yr
- -
TOTAL RECOMMENDED $44,307 $66,759 $34,614
383,626
kWh
$8,929
-
kW-mo/yr
$470 $294
TOTAL IMPLEMENTED $44,307 $66,759 $34,614
383,626
kWh
$8,929
-
kW-mo/yr
$470 $294
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs