| Assessment Year | 2010 |
|---|---|
| Principal Product | Treated Wastewater |
| NAICS | 221310: Water Supply and Irrigation Systems |
| SIC | 4941: Water Supply |
| Sales Range | less than $500 k |
| # of Employees | 56 |
| Plant Area |
962,737
ft2
|
| Annual Production | 6,205,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $192,346 | 2,131,791 |
kWh
|
$0.090 |
| Electricity Demand | $173,227 | 13,476 |
kW-mo/yr
|
$12.85 |
| Natural Gas | $487,708 | 74,175 |
MMBtu
|
$6.58 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $44,307 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $44,307 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4235: Remove or close off unneeded compressed air lines | $10,049 | $400 |
$8,208
90,967
kWh
|
$1,841
-
kW-mo/yr
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $255 | $31 |
$209
2,318
kWh
|
$46
-
kW-mo/yr
|
- | - | |
| 03 | 2.7132: Install timers on light switches in little used areas | $6,873 | $2,392 |
$5,751
63,733
kWh
|
$1,122
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $953 | $672 |
$158
1,751
kWh
|
$31
-
kW-mo/yr
|
$470 | $294 | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,157 | $2,712 |
$2,510
27,823
kWh
|
$647
-
kW-mo/yr
|
- | - | |
| 06 | 2.7135: Install occupancy sensors | $4,881 | $7,273 |
$3,917
43,411
kWh
|
$964
-
kW-mo/yr
|
- | - | |
| 07 | 2.7134: Use photocell controls | $11,135 | $19,068 |
$8,010
88,774
kWh
|
$3,125
-
kW-mo/yr
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,881 | $9,823 |
$2,402
26,625
kWh
|
$479
-
kW-mo/yr
|
- | - | |
| 09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,274 | $8,179 |
$1,903
21,090
kWh
|
$371
-
kW-mo/yr
|
- | - | |
| 10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,037 | $9,053 |
$867
9,608
kWh
|
$170
-
kW-mo/yr
|
- | - | |
| 11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $812 | $7,156 |
$679
7,526
kWh
|
$133
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $44,307 | $66,759 |
$34,614
383,626
kWh
|
$8,929
-
kW-mo/yr
|
$470 | $294 | ||
| TOTAL IMPLEMENTED | $44,307 | $66,759 |
$34,614
383,626
kWh
|
$8,929
-
kW-mo/yr
|
$470 | $294 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs