Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

390

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Other millwork (including flooring)
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
KS2427 #06 Y:2024 Use solar heat to make electricty $45,498 $453,376
KS2427 #05 Y:2024 Utilize higher efficiency lamps and/or ballasts $50,928 $156,644
KS2427 #04 Y:2024 Use cooling tower or economizer to replace chiller cooling $69,076 $156,917
KS2427 #03 Y:2024 Use optimum thickness insulation $9,550 $6,688
KS2427 #02 Y:2024 Reduce the pressure of compressed air to the minimum required $2,216 $90
KS2427 #01 Y:2024 Eliminate leaks in inert gas and compressed air lines/ valves $2,324 $5,480
NL0091 #05 Y:2023 Eliminate or reduce compressed air usage $216 $128
NL0091 #04 Y:2023 Utilize higher efficiency lamps and/or ballasts $507 $1,064
NL0091 #03 Y:2023 Eliminate leaks in inert gas and compressed air lines/ valves $1,370 $1,500
NL0091 #02 Y:2023 Utilize higher efficiency lamps and/or ballasts $16,289 $11,473
NL0091 #01 Y:2023 Improve air circulation with destratification fans / other methods $28,330 $57,285
WV0655 #11 Y:2023 Eliminate or reduce compressed air usage $324 $359
WV0655 #10 Y:2023 Reduce the pressure of compressed air to the minimum required $1,641 $210
WV0655 #09 Y:2023 Utilize energy-efficient belts and other improved mechanisms $4,005 $7,828
WV0655 #08 Y:2023 Develop a repair/replace policy $4,078 $12,517
WV0655 #07 Y:2023 Optimize plant power factor $6,154 $4,905
WV0655 #06 Y:2023 Insulate bare equipment $8,192 $5,240
WV0655 #05 Y:2023 Utilize higher efficiency lamps and/or ballasts $11,873 $10,662
WV0655 #04 Y:2023 Upgrade controls on compressors $11,948 $11,050
WV0655 #03 Y:2023 Establish a predictive maintenance program $12,350 $1,500