Assessment Year | 2024 |
---|---|
Principal Product | Hardwood Flooring |
NAICS | 321918: Other Millwork (including Flooring) |
SIC | 2426: Hardwood Dimension and Flooring Mills |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
58,800
ft2
|
Annual Production | 48,000
thousand feet
|
Production Hrs. Annual | 3,000
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $449,494 | 7,655,098 |
kWh
|
$0.059 | |
Electricity Demand | $293,283 | 20,081 |
kW-mo/yr
|
$14.60 | |
Electricity Fees | $3,579 | - |
|
- | |
Wood | $896,641 | 69,739 |
MMBtu
|
$12.86 | |
Waste Disposal Costs | |||||
Water Usage | $227,467 | 105,212 |
Tgal
|
$2.16 | |
TOTAL YEARLY COSTS | $1,870,464 | ||||
RECOMMENDED SAVINGS* | $150,588 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $30,590 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Wood Savings | Water Usage Savings | Personnel Changes Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2425: Use flue gases to heat process or service water | $50,347 | $17,230 | - | - | - |
$50,347
-
MMBtu
|
- | - | - | |
02 | 2.2128: Use steam condensate for hot water supply (non-potable) | $39,676 | $165,000 |
$(-14,030.0)
(-239,016)
kWh
|
- | - |
$34,336
-
MMBtu
|
$6,770
-
Tgal
|
- | $12,600 | |
03 | 2.4157: Establish a predictive maintenance program | $12,350 | $1,500 |
$8,955
152,547
kWh
|
$8,912
-
kW-mo/yr
|
- | - | - | $(-5,517.0) | - | |
04 | 2.4224: Upgrade controls on compressors | $11,948 | $11,050 |
$7,565
128,887
kWh
|
$4,383
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,873 | $10,662 |
$5,927
100,963
kWh
|
$5,946
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.2511: Insulate bare equipment | $8,192 | $5,240 | - | - | - |
$8,192
-
MMBtu
|
- | - | - | |
07 | 2.3212: Optimize plant power factor | $6,154 | $4,905 | - | - | $6,154 | - | - | - | - | |
08 | 2.4151: Develop a repair/replace policy | $4,078 | $12,517 |
$3,358
57,205
kWh
|
$1,140
-
kW-mo/yr
|
- | - | - | $(-420.0) | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,005 | $7,828 |
$2,632
44,844
kWh
|
$1,373
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,641 | $210 |
$1,031
17,557
kWh
|
$610
-
kW-mo/yr
|
- | - | - | - | - | |
11 | 2.4239: Eliminate or reduce compressed air usage | $324 | $359 |
$163
2,769
kWh
|
$161
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $150,588 | $236,501 |
$15,601
265,756
kWh
|
$22,525
-
kW-mo/yr
|
$6,154 |
$92,875
-
MMBtu
|
$6,770
-
Tgal
|
$(-5,937.0) | $12,600 | ||
TOTAL IMPLEMENTED | $30,590 | $27,654 |
$16,139
274,922
kWh
|
$12,196
-
kW-mo/yr
|
- |
$8,192
-
MMBtu
|
- | $(-5,937.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Wood Savings | Water Usage Savings | Personnel Changes Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs