Assessment Year | 2023 |
---|---|
Principal Product | Rubber belts |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 360 |
Plant Area |
649,000
ft2
|
Annual Production | 3,146,339
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,126,583 | 18,363,513 |
kWh
|
$0.061 |
Electricity Demand | $494,632 | 37,450 |
kW-mo/yr
|
$13.21 |
Natural Gas | $1,730,653 | 247,175 |
MMBtu
|
$7.00 |
TOTAL YEARLY COSTS | $3,351,868 | |||
RECOMMENDED SAVINGS* | $397,171 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4323: Use optimum size and capacity equipment | $4,951 | $31,059 |
$3,675
60,249
kWh
|
$1,276
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,711 | $360 |
$1,711
28,035
kWh
|
- | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $5,510 | $9,100 |
$4,090
67,047
kWh
|
$1,420
-
kW-mo/yr
|
- | - | |
04 | 2.2135: Repair and eliminate steam leaks | $8,146 | $1,330 | - | - |
$8,146
-
MMBtu
|
- | |
05 | 2.4239: Eliminate or reduce compressed air usage | $12,303 | $5,150 |
$11,944
195,783
kWh
|
$359
-
kW-mo/yr
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,575 | $28,807 |
$9,575
156,987
kWh
|
- | - | - | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $52,726 | $2,400 | - | - |
$52,726
-
MMBtu
|
- | |
08 | 2.3212: Optimize plant power factor | $126,570 | $196,842 | - |
$100,305
-
kW-mo/yr
|
- | $26,265 | |
09 | 2.9114: Use solar heat to make electricty | $175,679 | $545,812 |
$77,669
1,273,259
kWh
|
$98,010
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $397,171 | $820,860 |
$108,664
1,781,360
kWh
|
$201,370
-
kW-mo/yr
|
$60,872
-
MMBtu
|
$26,265 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs