Assessment Year | 2010 |
---|---|
Principal Product | Turbine Blades/Vanes |
NAICS | 336412: Aircraft Engine and Engine Parts Manufacturing |
SIC | 3724: Aircraft Engines and Engine Parts |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
115,000
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $220,017 | 3,815,894 |
kWh
|
$0.058 |
Electricity Demand | $81,994 | 10,513 |
kW-mo/yr
|
$7.80 |
Electricity Fees | $5,645 | - |
|
- |
Natural Gas | $99,213 | 7,307 |
MMBtu
|
$13.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,382 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,791 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,067 | - |
$6,067
126,400
kWh
|
- | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,276 | - |
$2,495
51,979
kWh
|
$781
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $3,995 | $1,245 |
$3,995
83,118
kWh
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,763 | $1,440 |
$3,763
78,400
kWh
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $267 | $492 |
$67
1,664
kWh
|
$16
-
kW-mo/yr
|
- | $184 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $142 | $817 |
$111
3,245
kWh
|
$31
-
kW-mo/yr
|
- | - | |
07 | 2.3212: Optimize plant power factor | $1,808 | $9,734 | - | - | $1,808 | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,680 | $17,732 |
$3,680
76,662
kWh
|
- | - | - | |
09 | 2.6211: Conserve energy by efficient use of vending machines | $108 | $516 |
$108
2,247
kWh
|
- | - | - | |
10 | 2.4321: Upgrade obsolete equipment | $276 | $1,831 |
$210
4,368
kWh
|
$66
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $23,382 | $33,807 |
$20,496
428,083
kWh
|
$894
-
kW-mo/yr
|
$1,808 | $184 | ||
TOTAL IMPLEMENTED | $13,791 | $4,580 |
$12,713
266,056
kWh
|
$894
-
kW-mo/yr
|
- | $184 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs