Assessment Year | 2024 |
---|---|
Principal Product | Roof Trusses |
NAICS | 321918: Other Millwork (including Flooring) |
SIC | 2439: Structural Wood Members, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 150 |
Plant Area |
290,000
ft2
|
Annual Production | 12,500
thousand feet
|
Production Hrs. Annual | 5,250
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $51,742 | 1,973,293 |
kWh
|
$0.026 | |
Electricity Demand | $76,464 | 4,468 |
kW-mo/yr
|
$17.11 | |
Electricity Fees | $10,492 | - |
|
- | |
Natural Gas | $177,671 | 13,306 |
MMBtu
|
$13.35 | |
Waste Disposal Costs | |||||
Water Usage | $2,790 | 449 |
Tgal
|
$6.21 | |
TOTAL YEARLY COSTS | $319,159 | ||||
RECOMMENDED SAVINGS* | $46,712 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $45,989 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $28,330 | $57,285 |
$(-478.7)
(-18,270)
kWh
|
$(-1,191.3)
-
kW-mo/yr
|
- | - | $30,000 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,289 | $11,473 |
$6,534
249,375
kWh
|
$9,755
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,370 | $1,500 |
$1,726
65,888
kWh
|
- | $(-256.0) | $(-100.0) | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $507 | $1,064 |
$105
3,994
kWh
|
$94
-
kW-mo/yr
|
$308 | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $216 | $128 |
$216
8,245
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $46,712 | $71,450 |
$8,102
309,232
kWh
|
$8,658
-
kW-mo/yr
|
$52 | $(-100.0) | $30,000 | ||
TOTAL IMPLEMENTED | $45,989 | $70,258 |
$7,781
296,993
kWh
|
$8,564
-
kW-mo/yr
|
$(-256.0) | $(-100.0) | $30,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs