64
matching recommendationsID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
WM0247 #06 Y:2025 | 06 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,959 | $1,750 |
n/a
|
WM0247 #05 Y:2025 | 05 | 2025 | Install occupancy sensors | $2,062 | - |
n/a
|
WM0247 #04 Y:2025 | 04 | 2025 | Utilize higher efficiency lamps and/or ballasts | $2,444 | $1,640 |
n/a
|
WM0247 #03 Y:2025 | 03 | 2025 | Reduce space conditioning during non-working hours | $2,473 | $2,950 |
n/a
|
WM0247 #02 Y:2025 | 02 | 2025 | Utilize energy-efficient belts and other improved mechanisms | $2,533 | $1,020 |
n/a
|
WM0247 #01 Y:2025 | 01 | 2025 | Reduce the pressure of compressed air to the minimum required | $7,641 | - |
n/a
|
NC0638 #05 Y:2019 | 05 | 2019 | Install occupancy sensors | $1,065 | $1,900 | |
NC0638 #04 Y:2019 | 04 | 2019 | Utilize higher efficiency lamps and/or ballasts | $544 | $2,464 | |
NC0638 #03 Y:2019 | 03 | 2019 | Recover heat from exhausted steam, hot air or hot water | $6,164 | $6,700 | |
NC0638 #02 Y:2019 | 02 | 2019 | Install / repair insulation on steam lines | $5,807 | $3,600 | |
NC0638 #01 Y:2019 | 01 | 2019 | Use waste heat from hot flue gases to preheat | $18,797 | $85,000 | |
LE0478 #06 Y:2019 | 06 | 2019 | Use adjustable frequency drive or multiple speed motors on existing system | $2,884 | $9,000 | |
LE0478 #05 Y:2019 | 05 | 2019 | Utilize energy-efficient belts and other improved mechanisms | $187 | $450 | |
LE0478 #04 Y:2019 | 04 | 2019 | Preheat combustion air with waste heat | $39,339 | $85,000 | |
LE0478 #03 Y:2019 | 03 | 2019 | Repair or replace steam traps | $11,891 | $9,000 | |
LE0478 #02 Y:2019 | 02 | 2019 | Reduce the pressure of compressed air to the minimum required | $667 | $60 | |
LE0478 #01 Y:2019 | 01 | 2019 | Install timers and/or thermostats | $2,876 | - | |
LE0345 #11 Y:2012 | 11 | 2012 | Install / repair insulation on steam lines | $53,742 | $3,200 | |
LE0345 #10 Y:2012 | 10 | 2012 | Utilize energy-efficient belts and other improved mechanisms | $4,720 | $7,500 | |
LE0345 #09 Y:2012 | 09 | 2012 | Use hot process fluids to preheat incoming process fluids | $3,306 | $3,800 |