ITAC Assessment: WV0691
ITAC logo
ITAC Assessment: WV0691
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Steel studs, track & accessories
NAICS 332322: Sheet Metal Work Manufacturing
SIC 3444: Sheet Metal Work
Sales Range $100
M
to 500
M
# of Employees 154
Plant Area 362,000
ft2
Annual Production 115,392,720
lb
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,028 2,197,107
kWh
Electricity Demand $61,886 5,866
kW-mo/yr
Electricity Fees $27,077 -
Natural Gas $41,154 4,684
MMBtu
TOTAL YEARLY COSTS $215,145
RECOMMENDED SAVINGS* $79,777 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $35,475 $103,505 $19,977
380,968
kWh
$15,498
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $23,407 $43,263 $15,220
393,272
kWh
$8,187
-
kW-mo/yr
-
03 2.4224: Upgrade controls on compressors $4,889 $2,661 $3,349
86,531
kWh
$1,540
-
kW-mo/yr
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,884 $791 $3,207
82,860
kWh
$1,677
-
kW-mo/yr
-
05 2.7241: Install outside air damper / economizer on hvac unit $3,361 $8,020 $2,665
68,855
kWh
$696
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,748 $5,805 $1,631
42,134
kWh
$1,117
-
kW-mo/yr
-
07 2.4157: Establish a predictive maintenance program $1,258 $5,200 $1,869
48,293
kWh
$981
-
kW-mo/yr
$(-1,592.0)
08 2.6231: Utilize controls to operate equipment only when needed $1,158 $1,551 $768
19,843
kWh
$390
-
kW-mo/yr
-
09 2.4221: Install compressor air intakes in coolest locations $988 $3,325 $650
16,807
kWh
$338
-
kW-mo/yr
-
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $803 $1,648 $529
13,678
kWh
$274
-
kW-mo/yr
-
11 2.4239: Eliminate or reduce compressed air usage $499 $1,904 $330
8,515
kWh
$169
-
kW-mo/yr
-
12 2.4231: Reduce the pressure of compressed air to the minimum required $307 $74 $201
5,193
kWh
$106
-
kW-mo/yr
-
TOTAL RECOMMENDED $79,777 $177,747 $50,396
1,166,949
kWh
$30,973
-
kW-mo/yr
$(-1,592.0)
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs