Assessment Year | 1998 |
---|---|
Principal Product | Powdered metal parts |
NAICS |
n/a
|
SIC | 3462: Iron and Steel Forgings |
Sales Range | $5 M to 10M |
# of Employees | 93 |
Plant Area |
48,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $148,620 | 5,248,535 |
kWh
|
$0.028 |
Electricity Demand | $91,100 | - |
|
- |
Electricity Fees | $8,002 | - |
|
- |
Natural Gas | $27,693 | 4,544 |
MMBtu
|
$6.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,717 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,604 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $14,801 | $1,936 |
$14,801
328,253
kWh
|
- | - | - | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $1,344 | $1,516 |
$1,344
29,894
kWh
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $850 | $110 |
$850
29,894
kWh
|
- | - | - | - | |
04 | 2.7224: Reduce space conditioning during non-working hours | $526 | $242 |
$526
34,291
kWh
|
- | - | - | - | |
05 | 2.7135: Install occupancy sensors | $360 | $532 |
$360
12,603
kWh
|
- | - | - | - | |
06 | 2.8113: Purchase gas directly from a contract gas supplier | $7,243 | - | - |
$7,243
-
MMBtu
|
- | - | - | |
07 | 4.513: Re-arrange equipment layout to reduce labor costs | $7,200 | $288 | - | - | - | - | $7,200 | |
08 | 3.5316: Contract a wood pallet recycling company | $2,160 | - | - | - | - |
$2,160
-
lb
|
- | |
09 | 3.4155: Meter waste water | $233 | - | - | - |
$233
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $34,717 | $4,624 |
$17,881
434,935
kWh
|
$7,243
-
MMBtu
|
$233
-
Tgal
|
$2,160
-
lb
|
$7,200 | ||
TOTAL IMPLEMENTED | $25,604 | $2,866 |
$16,011
370,750
kWh
|
- |
$233
-
Tgal
|
$2,160
-
lb
|
$7,200 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs