ITAC Assessment: WV0651
ITAC logo
ITAC Assessment: WV0651
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Vending machines
NAICS 333310: Commercial and Service Industry Machinery Manufacturing
SIC 3581: Automatic Vending Machines
Sales Range $10
M
to 50
M
# of Employees 94
Plant Area 75,100
ft2
Annual Production 434,760
units
Production Hrs. Annual 5,250
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,752 879,240
kWh
Electricity Demand $33,957 2,302
kW-mo/yr
LPG $5,114 256
MMBtu
TOTAL YEARLY COSTS $87,823
RECOMMENDED SAVINGS* $20,217 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,035

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $10,789 $14,056 $5,951
109,521
kWh
$4,838
-
kW-mo/yr
-
02 2.4224: Upgrade controls on compressors $2,502 $2,082 $1,764
31,842
kWh
$738
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,830 $2,314 $1,137
20,522
kWh
$693
-
kW-mo/yr
-
04 2.7447: Install vinyl strip / high speed / air curtain doors $930 $2,863 $(-10.0)
(-183)
kWh
- $940
-
MMBtu
05 2.6231: Utilize controls to operate equipment only when needed $928 $823 $928
16,748
kWh
- -
06 2.4239: Eliminate or reduce compressed air usage $846 $228 $521
9,410
kWh
$325
-
kW-mo/yr
-
07 2.4221: Install compressor air intakes in coolest locations $854 $4,011 $398
7,181
kWh
$236
-
kW-mo/yr
$220
-
MMBtu
08 2.6232: Install set-back timers $608 $1,271 $283
5,107
kWh
$325
-
kW-mo/yr
-
09 2.4231: Reduce the pressure of compressed air to the minimum required $430 $217 $268
4,844
kWh
$162
-
kW-mo/yr
-
10 2.4322: Use or replace with energy efficient substitutes $360 $1,750 $227
4,095
kWh
$133
-
kW-mo/yr
-
11 2.1233: Analyze flue gas for proper air/fuel ratio $140 $656 - - $140
-
MMBtu
TOTAL RECOMMENDED $20,217 $30,271 $11,467
209,087
kWh
$7,450
-
kW-mo/yr
$1,300
-
MMBtu
TOTAL IMPLEMENTED $14,035 $17,471 $7,877
144,297
kWh
$6,018
-
kW-mo/yr
$140
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs