| Assessment Year | 2023 |
|---|---|
| Principal Product | Vending machines |
| NAICS | 333310: Commercial and Service Industry Machinery Manufacturing |
| SIC | 3581: Automatic Vending Machines |
| Sales Range | $10 M to 50M |
| # of Employees | 94 |
| Plant Area |
75,100
ft2
|
| Annual Production | 434,760
units
|
| Production Hrs. Annual | 5,250
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $48,752 | 879,240 |
kWh
|
$0.055 |
| Electricity Demand | $33,957 | 2,302 |
kW-mo/yr
|
$14.75 |
| LPG | $5,114 | 256 |
MMBtu
|
$19.98 |
| TOTAL YEARLY COSTS | $87,823 | |||
| RECOMMENDED SAVINGS* | $20,217 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,035 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,789 | $14,056 |
$5,951
109,521
kWh
|
$4,838
-
kW-mo/yr
|
- | |
| 02 | 2.4224: Upgrade controls on compressors | $2,502 | $2,082 |
$1,764
31,842
kWh
|
$738
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,830 | $2,314 |
$1,137
20,522
kWh
|
$693
-
kW-mo/yr
|
- | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $930 | $2,863 |
$(-10.0)
(-183)
kWh
|
- |
$940
-
MMBtu
|
|
| 05 | 2.6231: Utilize controls to operate equipment only when needed | $928 | $823 |
$928
16,748
kWh
|
- | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $846 | $228 |
$521
9,410
kWh
|
$325
-
kW-mo/yr
|
- | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $854 | $4,011 |
$398
7,181
kWh
|
$236
-
kW-mo/yr
|
$220
-
MMBtu
|
|
| 08 | 2.6232: Install set-back timers | $608 | $1,271 |
$283
5,107
kWh
|
$325
-
kW-mo/yr
|
- | |
| 09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $430 | $217 |
$268
4,844
kWh
|
$162
-
kW-mo/yr
|
- | |
| 10 | 2.4322: Use or replace with energy efficient substitutes | $360 | $1,750 |
$227
4,095
kWh
|
$133
-
kW-mo/yr
|
- | |
| 11 | 2.1233: Analyze flue gas for proper air/fuel ratio | $140 | $656 | - | - |
$140
-
MMBtu
|
|
| TOTAL RECOMMENDED | $20,217 | $30,271 |
$11,467
209,087
kWh
|
$7,450
-
kW-mo/yr
|
$1,300
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $14,035 | $17,471 |
$7,877
144,297
kWh
|
$6,018
-
kW-mo/yr
|
$140
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs