Assessment Year | 2009 |
---|---|
Principal Product | purified water and carbonated soft drinks |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $50 M to 100M |
# of Employees | 110 |
Plant Area |
17,500
ft2
|
Annual Production | 23,000,000
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $838,834 | 9,786,420 |
kWh
|
$0.086 |
Electricity Demand | $191,416 | 21,088 |
kW-mo/yr
|
$9.08 |
Electricity Fees | $122,049 | - |
|
- |
Natural Gas | $265,399 | 65,979 |
MMBtu
|
$4.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $251,187 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $64,004 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7124: Make a practice of turning off lights when not needed | $1,635 | - |
$1,635
19,233
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,766 | - |
$19,530
198,556
kWh
|
$236
-
kW-mo/yr
|
- | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $4,130 | - |
$4,080
41,487
kWh
|
$50
-
kW-mo/yr
|
- | |
04 | 2.7141: Lower light fixtures in high ceiling areas | $1,899 | - |
$1,881
19,067
kWh
|
$18
-
kW-mo/yr
|
- | |
05 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $334 | - | - | - |
$334
-
MMBtu
|
|
06 | 2.4133: Use most efficient type of electric motors | $12,625 | - |
$12,445
122,205
kWh
|
$180
-
kW-mo/yr
|
- | |
07 | 2.2442: Preheat combustion air with waste heat | $45,514 | - | - | - |
$45,514
-
MMBtu
|
|
08 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $2,119 | - |
$2,119
20,182
kWh
|
- | - | |
09 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $19,795 | - |
$19,795
188,529
kWh
|
- | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,346 | - |
$2,346
22,344
kWh
|
- | - | |
11 | 2.4221: Install compressor air intakes in coolest locations | $14,435 | - |
$14,435
169,828
kWh
|
- | - | |
12 | 2.6231: Utilize controls to operate equipment only when needed | $16,025 | - |
$16,025
188,529
kWh
|
- | - | |
13 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $42,269 | - |
$42,269
402,561
kWh
|
- | - | |
14 | 2.4231: Reduce the pressure of compressed air to the minimum required | $68,295 | - |
$68,295
650,425
kWh
|
- | - | |
TOTAL RECOMMENDED | $251,187 | - |
$204,855
2,042,946
kWh
|
$484
-
kW-mo/yr
|
$45,848
-
MMBtu
|
||
TOTAL IMPLEMENTED | $64,004 | - |
$63,434
620,350
kWh
|
$236
-
kW-mo/yr
|
$334
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs