ITAC Assessment: UF0429
ITAC logo
ITAC Assessment: UF0429
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product purified water and carbonated soft drinks
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 110
Plant Area 17,500
ft2
Annual Production 23,000,000
units
Production Hrs. Annual 2,080
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $838,834 9,786,420
kWh
Electricity Demand $191,416 21,088
kW-mo/yr
Electricity Fees $122,049 -
Natural Gas $265,399 65,979
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $251,187 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $64,004

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7124: Make a practice of turning off lights when not needed $1,635 - $1,635
19,233
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $19,766 - $19,530
198,556
kWh
$236
-
kW-mo/yr
-
03 2.7111: Reduce illumination to minimum necessary levels $4,130 - $4,080
41,487
kWh
$50
-
kW-mo/yr
-
04 2.7141: Lower light fixtures in high ceiling areas $1,899 - $1,881
19,067
kWh
$18
-
kW-mo/yr
-
05 2.1131: Repair faulty insulation in furnaces, boilers, etc $334 - - - $334
-
MMBtu
06 2.4133: Use most efficient type of electric motors $12,625 - $12,445
122,205
kWh
$180
-
kW-mo/yr
-
07 2.2442: Preheat combustion air with waste heat $45,514 - - - $45,514
-
MMBtu
08 2.1131: Repair faulty insulation in furnaces, boilers, etc $2,119 - $2,119
20,182
kWh
- -
09 2.4222: Install adequate dryers on air lines to eliminate blowdown $19,795 - $19,795
188,529
kWh
- -
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,346 - $2,346
22,344
kWh
- -
11 2.4221: Install compressor air intakes in coolest locations $14,435 - $14,435
169,828
kWh
- -
12 2.6231: Utilize controls to operate equipment only when needed $16,025 - $16,025
188,529
kWh
- -
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $42,269 - $42,269
402,561
kWh
- -
14 2.4231: Reduce the pressure of compressed air to the minimum required $68,295 - $68,295
650,425
kWh
- -
TOTAL RECOMMENDED $251,187 - $204,855
2,042,946
kWh
$484
-
kW-mo/yr
$45,848
-
MMBtu
TOTAL IMPLEMENTED $64,004 - $63,434
620,350
kWh
$236
-
kW-mo/yr
$334
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs