Assessment Year | 2021 |
---|---|
Principal Product | OEM Mining Equipment |
NAICS | 333131: Mining Machinery and Equipment Manufacturing |
SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 29 |
Plant Area |
170,000
ft2
|
Annual Production | 4,000
ton
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $139,932 | 1,623,520 |
kWh
|
$0.086 |
Electricity Demand | $16,317 | 1,547 |
kW-mo/yr
|
$10.55 |
Electricity Fees | $4,532 | - |
|
- |
Natural Gas | $23,641 | 2,795 |
MMBtu
|
$8.46 |
TOTAL YEARLY COSTS | $184,422 | |||
RECOMMENDED SAVINGS* | $46,493 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,534 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $32,464 | $14,300 |
$27,805
322,194
kWh
|
$4,659
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,495 | $38,306 |
$7,195
83,465
kWh
|
$2,300
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,836 | $1,100 |
$2,425
28,134
kWh
|
$411
-
kW-mo/yr
|
- | |
04 | 2.3132: Recharge batteries on during off-peak demand periods | $952 | - | - |
$2,152
-
kW-mo/yr
|
$(-1,200.0) | |
05 | 2.4151: Develop a repair/replace policy | $746 | $300 |
$977
11,333
kWh
|
$169
-
kW-mo/yr
|
$(-400.0) | |
TOTAL RECOMMENDED | $46,493 | $54,006 |
$38,402
445,126
kWh
|
$9,691
-
kW-mo/yr
|
$(-1,600.0) | ||
TOTAL IMPLEMENTED | $4,534 | $1,400 |
$3,402
39,467
kWh
|
$2,732
-
kW-mo/yr
|
$(-1,600.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs