Assessment Year | 1993 |
---|---|
Principal Product | tool storage chest |
NAICS |
n/a
|
SIC | 2542: Office and Store Fixtures, Partitions, Shelving, and Lockers, Except Wood |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
100,000
ft2
|
Annual Production | 13,000,000
lb
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $287,509 | 6,636,577 |
kWh
|
$0.043 |
Natural Gas | $122,935 | 43,826 |
MMBtu
|
$2.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,194 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,673 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6121: Reduce hot water temperature to the minimum required | $19,340 | $50,000 |
$886
20,516
kWh
|
$18,454
-
MMBtu
|
|
02 | 2.7314: Reduce ventilation air | $8,534 | $30,000 |
$(-2,692.0)
(-62,134)
kWh
|
$11,226
-
MMBtu
|
|
03 | 2.4239: Eliminate or reduce compressed air usage | $5,141 | $100 |
$5,141
118,699
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,145 | $240 |
$3,145
72,685
kWh
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,470 | $200 |
$1,470
33,998
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,629 | $518 |
$4,629
106,975
kWh
|
- | |
07 | 2.7135: Install occupancy sensors | $2,044 | $2,646 |
$2,044
47,186
kWh
|
- | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $891 | $720 |
$891
20,516
kWh
|
- | |
TOTAL RECOMMENDED | $45,194 | $84,424 |
$15,514
358,441
kWh
|
$29,680
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,673 | $3,164 |
$6,673
154,161
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs